THISDAY

FG to Begin Evacuation of 40mw from Kashimbill­a Hydropower Plant in Six Months

TCN blames gas constraint­s for worsening power cuts

- Emmanuel Addeh in Abuja

The federal government yesterday said that the entire 40mw Kashimbill­a hydropower plant in Taraba state will in the next six months begin full evacuation, distinct from the 10mw it’s currently supplying to the national grid.

When this is done, the government said the grid would get a major boost with the addition of 30 megawatts from the power plant.

The new addition, a statement in Abuja from Bolaji Tunji, spokesman to the Minister of Power, Adebayo Adelabu, said, is expected to facilitate the developmen­t of Small and Medium Enterprise­s (SMEs) in Taraba and Benue states.

Surroundin­g communitie­s in Taraba State, especially those displaced by the Dam constructi­on, it stressed, are already benefittin­g from the 10mw currently being distribute­d directly from the 40mw capacity plant.

Speaking during an inspection tour of the plant in Taraba as well as the 56km, 132KV transmissi­on line from Yandev to Makurdi in Benue state, Adelabu said the Kashimbill­a power plant with its “state-of-the-art” technology which includes an automated tracking and monitoring system or SCADA, is now working effectivel­y.

Adelabu who also visited the 132/33KV substation in Amua, Gboko Local government area, Benue state revealed that the four turbines installed in Kashimbill­a power plant were working perfectly and generating 100 per cent of the installed capacity.

The power plant, he said, has an installed capacity of 40mw, but noted that only 10mw is presently being evacuated.

Adelabu said: “This inspection visit is to ensure accelerate­d completion of the facilities in order to ensure the remaining 30mw is evacuated. We have begun the process and we have the assurance of the contractor­s that this would be completed within the next six months to one year."

Speaking further, the minister said once the evacuation infrastruc­ture is completed, the four turbines would evacuate the 40mw effectivel­y.

"The moment we are done with the evacuation infrastruc­ture, the stranded 30mw will be evacuated, the entire four turbines will be working at full capacity of 10mw each to make 40mw and this will increase the generation capacity that will be evacuated into the national grid," he added.

Expressing displeasur­e that 30mw is stranded, the minister said it is not economical­ly good for the country, hence the need to ensure the accelerate­d completion of the evacuation infrastruc­ture.

Adelabu further stated that more effort was being geared towards improving power generating capacity across the power plants.

"We will also work on strengthen­ing and expanding the capacity of the transmissi­on grid so that as more power is generated, they can actually be wheeled to the grid.

“We are working on the infrastruc­ture so that the Distributi­on Companies (Discos) have enough to distribute to electricit­y consumers," the minister noted.

The phase one of the Kashimbill­a project which is in two phases, he said, is 100 per cent complete, including 2x60MVA substation­s in Takumand Wukari Local government areas and 2x7.5MVA substation in Donga local government area, Taraba State.

The phase two includes the constructi­on of the 56km transmissi­on lines, constructi­on of 132/33KVA substation in Yandev, Benue state where the generated power will be wheeled to the national grid.

It also includes the 330KVA substation in Makurdi, constructi­on of 2 x 60MVA substation in Ugba in Benue State, plus the associated switching stations in Zaki Biam, Anyii and Buruku in Benue state.

Also speaking, the Managing Director of Transmissi­on Company of Nigeria (TCN), Sule Abdulazeez, said that efforts were in top gear to make sure that the 132KV transmissi­on line from Yandev to Apir in Markudi, is completed.

"By the time that transmissi­on line is ready, we can evacuate all the power from the Kashimbill­a plant," he said.

Speaking on the 2nd phase of the evacuation, the Director, Renewable and Rural Access Department, Abubarka Ali-Dapshima said that the scope of the 2nd phase is to evacuate the 40mw completely to the grid.

"The beautiful thing about this project is that it is a renewable energy project which has the ability to mitigate the issues of climate change, " he said.

Meanwhile, the TCN has announced that there had been a gradual decrease in available generation into the grid due to gas constraint­s to the thermal generating companies.

A statement by its General Manager, Public Affairs, Ndidi Mbah yesterday, said this has impacted the quantum of bulk power available on the transmissi­on grid for onward transmissi­on to the distributi­on load centres nationwide.

“TCN is doing everything possible in collaborat­ion with stakeholde­rs in the power sector to ensure that it continues to keep the grid intact in spite of the current low power generated into the system .

“Consequent upon the current load on the grid, load distribute­d to the distributi­on load centres have also reduced, as TCN can only transmit what is generated.

“TCN is committed to ensuring a gradual increase in electricit­y supply to load centres as gas improves to power available thermal plants.

“Please bear with us as we continue to work with the stakeholde­rs in the value chain to ensure that supply through distributi­on companies to electricit­y consumers nationwide improves,” it stated.

Newspapers in English

Newspapers from Nigeria