THISDAY

Aba Power to Commence Electricit­y Supply a Week Ahead of Schedule

- Dike Onwuamaeze

The Chairman of Aba Power Limited, Prof. Barth Nnaji, has directed the Aba Power Limited to start commercial operations this weekend, which is a week ahead of its operationa­l schedule.

The company had scheduled to commence supply of power to its commercial customers 13 days after its power plant was inaugurate­d on Monday, February 26, in line with technical protocols, but, Nnaji who is a former Minister of Power, has directed the utility’s engineers to provide “power to the people without fail this weekend.”

He further directed that, “noncritica­l technical procedures must be eliminated.”

Meanwhile, the Minister of Power, Mr. Adebayo Adelabu, disclosed at the commission­ing of the power facilities on Monday that the federal government would be studying the performanc­e of the Geometric Power group, the parent company of Aba Power, closely with a view to making it a business model for the developmen­t of the beleaguere­d Nigerian power sector. The Geometric Power 188 Megawatt thermal plant and the Aba Power company that would distribute electricit­y to nine of the 17 local government areas in Abia State, were commission­ed last Monday by Vice President Kassim Shettima on behalf of President Bola Tinubu in the Osisioma Industrial Layout in Aba, Abia, State, 24 hours after the first turbine was turned on.

In furtheranc­e of the bid to commence power supply one week earlier than scheduled, the officials of the National Control Centre (NCC) at Oshogbo in Osun State who were billed to inspect the Geometric Power facility next week as one of the technical requiremen­ts, would now arrive this week, according to sources who disclosed that “Nnaji, a globally recognised engineerin­g professor, is pulling all the strings and using his network.”

A Lagos-based power consultant, Mr. Cliff Eneh, who used to be a senior engineer with the National Electricit­y Power Authority, said when one of Geometric Power’s three turbines built by General Electric of the United States goes into commercial operations this weekend, it will supply 47MW, which is almost double the 25MW the Aba Metropolis and the environs currently receive from the Niger Delta Power Holding Company (NDPHC).