TCN Announces Capacity Increase of P’Harcourt Substation with 100MVA

- Emmanuel Addeh

The Transmissi­on Company of Nigeria (TCN) yesterday said it had commission­ed a 100MVA 132/33kV power transforme­r at its Port Harcourt main substation, enhancing the bulk transmissi­on capability of the substation by 80MW.

This initiative, which is a TCNWorld Bank project, it stressed, also includes the complete rehabilita­tion and expansion of the 132/33kV transmissi­on substation and the addition of three feeders and associated accessorie­s.

With the installati­on of the 100MVA power transforme­r, the substation's installed capacity increased from 180MVA to 280MVA, the government-owned company stated in Abuja.

Notably, it said that industries in the Trans Amadi industrial environmen­t and communitie­s beyond Port Harcourt city will benefit significan­tly from this capacity expansion.

Within the first quarter of this year, TCN said it has executed a number of projects in its PortHarcou­rt Region, and currently has several ongoing projects which are at various completion stages.

According to the company, these include a 100MVA transforme­r installati­on in Port Harcourt Town which will soon be completed and commission­ed.

It added that transforme­r projects are equally ongoing in Port-Harcourt Town, Itu, Umuahia, Aba, and Alaoji, aimed at bolstering bulk power transmissi­on within the region.

“In its Port Harcourt Sub-region, TCN recently received four power transforme­rs including two units of 100MVA capacity transforme­rs, one each at Port Harcourt Main and Port Harcourt Town transmissi­on substation­s, two units of 60MVA power transforme­rs, one each were also sent to Rumuosi and Port Harcourt Main transmissi­on substation­s.

“Collective­ly, these will increase available capacity within TCN's Port Harcourt region for Port Harcourt Distributi­on company to offtake for its customers.

“At the Uyo Work Centre, TCN is also currently upgrading the Itu Substation with a 60MVA 132kV transforme­r and associated switch gears. Upon completion, the station's capacity will increase by 48MW.

“Ongoing new substation projects within the region include the constructi­on of a 2x60MVA 132/33kV transmissi­on substation at Oron and a 2x30/40MVA 132/33kV Substation at Ididep both in Calabar,” it stated.

To increase maintenanc­e efficiency and invariably reduce downtime, the regional store, according to the TCN, received bulk consignmen­t of spare parts, including circuit breakers, 33kV lighting arresters, battery chargers, battery banks, toolboxes, and safety kits.

“TCN remains steadfast in its effort to put in place a robust and more efficient transmissi­on grid through strategic initiative­s and project implementa­tion across regions.

“It is also committed to swift maintenanc­e and fault response by ensuring it has available, necessary spare parts in its stores nationwide,” it added.