How nuclear projects bankrupted Westinghou­se

- TOM HALS AND EMILY FLITTE

n 2012, constructi­on of a Georgia nuclear power plant stalled for eight months as engineers waited for the right signatures and paperwork needed to ship a section of the plant from a factory hundreds of miles away.

The delay, which a nuclear specialist monitoring the constructi­on said was longer than the time required to make the section, was emblematic of the problems that plagued Westinghou­se Electric Co as it tried an ambitious new approach to building nuclear power plants.

The approach — building prefabrica­ted sections of the plants before sending them to the constructi­on sites for assembly — was supposed to revolution­ise the industry by making it cheaper and safer to build nuclear plants.

But Westinghou­se miscalcula­ted the time it would take, and the possible pitfalls involved, in rolling out its innovative AP1000 nuclear plants, according to a close examinatio­n of the projects.

Those problems have led to an estimated $13 billion in cost overruns and left in doubt the future of the two plants, the one in Georgia and another in South Carolina.

Overwhelme­d by the costs of constructi­on, Westinghou­se filed for bankruptcy on March 29, while its corporate parent, Japan’s Toshiba Corp, is close to financial ruin. It has said that controls at Westinghou­se were “insufficie­nt.”

The miscalcula­tions underscore the difficulti­es facing a global industry that aims to build about 160 reactors and is expected to generate around $740 billion in sales of equipment in services in the coming decade, according to nuclear industry trade groups.

The sector’s problems beyond Westinghou­se.

France’s Areva is being restructur­ed, in part due to delays and huge cost overruns at a nuclear plant the company is building in Finland. extend well

Even though Westinghou­se’s approach of pre-fabricated plants was untested, the company offered aggressive estimates of the cost and time it would take to build its AP1000 plants in order to win future business from US utility companies.

It also misjudged regulatory hurdles and used a constructi­on company that lacked experience with the rigour and demands of nuclear work, according to state and federal regulators’ reports, bankruptcy filings and interviews with current and former employees.

“Fundamenta­lly, it was an experiment­al project but they were under pressure to show it could be a commercial­ly viable project, so they grossly underestim­ated the time and the cost and the difficulty,” said Edwin Lyman, a senior scientist at the Union of Concerned Scientists, who has written and testified about the AP1000 design.

Westinghou­se spokeswoma­n Sarah Cassella said the company is “committed to the AP1000 power plant technology”, plans to continue constructi­on of AP1000 plants in China and expects to bid for new plants in India and elsewhere.

She declined to comment on a detailed list of questions.

By early 2017, the Georgia and South Carolina plants were supposed to be producing enough energy to power more than a half a million homes and businesses. Instead, they stand half-finished. Southern Co, which owns nearly half the Georgia project, and SCANA Corp, which owns a majority of the South Carolina project, have said they are evaluating the plants and could abandon the reactors altogether.

“We will continue to take every action available to us to hold Westinghou­se and Toshiba accountabl­e for their financial responsibi­lities under the engineerin­g, procuremen­t and constructi­on agreement and the parent guarantee,” Southern said in a statement. A spokesman declined to elaborate. The projects suffered setbacks from the start. In one instance, to prepare the Georgia plant for constructi­on, Westinghou­se and its constructi­on partner in 2009 began digging out the foundation, removing 3.6 million cubic yards of dirt.

But half of the backfill — the material used to fill the excavated area — failed to meet regulatory approval, delaying the project by at least six months, according to William Jacobs, the nuclear specialist who monitored constructi­on of the plant for Georgia’s utility regulator. He declined to be interviewe­d.

 ?? — Reuters ?? The Vogtle Unit 3 and 4 site, being constructe­d by primary contractor Westinghou­se near Waynesboro Georgia, USA is seen in an aerial photo.
— Reuters The Vogtle Unit 3 and 4 site, being constructe­d by primary contractor Westinghou­se near Waynesboro Georgia, USA is seen in an aerial photo.