Oman Oil Refineries and Petroleum Industries Company’s (Orpic) Mina al Fahal Refinery undergoes a major planned turnaround and maintenanc­e activity for 45 days on October 3 to November 16, 2017.

Comes to ensure that Orpic’s operations run safely and smoothly at all times, this shutdown will be used to execute a number of maintenanc­e activities in order to improve the operationa­l performanc­e of the refinery.

This planned turnaround is undertaken every 4 years to carry out Inspection and testing, debottlene­cking projects, revamps and catalyst regenerati­on that are much needed to ensure refinery reliabilit­y and improved efficiency of all its downstream units.

The 45-day maintenaic­e period will cover modificati­ons to the existing plant to allow a full integratio­n of the new units, being constructe­d under the Suhar Refinery Improvemen­t Project (SRIP) and Muscat-Suhar Product Pipeline (MSPP) project including a distributi­on depot in Jifnain, that are due for commission­ing later in the year. All product supply during the period of the turnaround has been meticulous­ly scheduled through all Orpic’s delivery points to ensure smooth product delivery to all local marketing companies.

The turnaround is expected to have a total workforce of 2,200 and anticipate­d 1,000,000 man-hours at site.

 ??  ??