Plans unveiled for Oman’s biggest water project

-

FROM P13 decommissi­oned later this upon the expiry of its Water Purchase Agreement with OPWP. All five water units with a current capacity of 140,000 m3/day (31 MIGD) but based on old-style Multi-Stage Flash (MSF) technology, will be pulled out of service when the company’s water supply agreement with the government comes to an end in September this year.

Ghubrah III IWP, which will be fully operationa­l by 2022, will help augment desalinati­on capacity in a region that continues to witness strong water demand growth estimated at 5 per cent annually.

Water demand in the Main Interconne­cted Zone — encompassi­ng the governorat­es of Muscat, Al Batinah North, Al Batinah South, Buraimi, Al Dakhiliyah, and Al Dhahirah — is projected to increase from 746,000 m3/d in 2016 to around 1.065 million m3/d in 2023.

In the Sharqiyah Zone, water demand is expected to increase at the rate of 7 per cent, from 93,000 m3/d in 2016 to 115,000 m3/d in 2023.

In the interim, burgeoning water demand in the Interconne­cted Zone will be met by two major Independen­t Water Projects (IWP) currently nearing completion in Barka and Suhar on the Sultanate’s Batinah coast.

Barka IV IWP, a 281,000 m3/day (62 MIGD) capacity plant under developmen­t by Barka Desalinati­on Company, is set to be operationa­l by the middle of this year. Sohar III IWP, on the other hand, a 250,000 m3/day (55 MIGD) plant being constructe­d by Myah Gulf Desalinati­on Company, will commence commercial operations in the third quarter of this year.

To cater to longer term water demand, OPWP is weighing plans to procure a new 200,000 m3/day (44 MIGD) capacity water scheme in North Al Batinah for launch in 2022.