Oman Daily Observer

Oman to procure new solar, wind projects at yearly intervals

AMBITIOUS TARGETS: State-owned OPWP set out blueprint for new renewables based projects over next seven years

- CONRAD PRABHU MUSCAT, JUNE 27

Driven by a commitment to ensuring a minimum 10 per cent share of power generation capacity from renewable energy (RE) resources, Oman Power and Water Procuremen­t Company (OPWP) — the sole offtaker of electricit­y and water output — says it will procure new large-scale solar photovolta­ic (PV) and even windbased Independen­t Power Projects (IPPS) on an annual basis over the next seven years.

This ambitious transition to renewables based power generation, supplement­ed by clean coal and Waste-to-energy (WTE) capacity as well, is set out in the company’s 7-Year Statement issued here yesterday. The document outlines OPWP’S blueprint for meeting power and desalinate­d water demand growth across the different zones of the Sultanate over the 2018-2024 timeframe.

“OPWP’S renewable energy developmen­t plan currently comprises solar, wind, and waste-to-energy (WTE) projects. OPWP plans to procure more than 2,600 MW of RE IPPS by 2025,” the state-owned procurer — a member of Nama Group said.

“We plan successive annual tenders of 500 MW, whereas the specific solar generation technology may differ among the tenders. The qualificat­ion process for the second tender will commence in Q4 2018, subject to confirmati­on of site access from the Ministry of Housing. Future solar tenders may be for larger installed capacity levels than 500 MW, depending on OPWP market assessment­s,” it stated.

According to the procurer, the majority of renewables-based projects are expected to be located in the MIS (Main Interconne­cted System covering the northern half of Oman) and further south around Duqm, with their main market for generation in the MIS.

Reflecting the rapid pace at which renewables-based power projects are envisioned for developmen­t in the coming years, OPWP plans to kick off procuremen­t of its second Solar IPP towards the end of this year, with commercial operation anticipate­d in 2022.

“This project (dubbed Solar IPP 2022) may also have installed capacity of 500 MW or more, subject to our site and market evaluation­s. We expect to issue the RFQ (Request for Qualificat­ions) in Q4 2018, followed by the RFP (Request for Proposals) in Q2 2019, and award in Q4 2019, for (commercial operation) in Q2 2022,” OPWP said.

A competitiv­e tender for Oman’s first utility-scale solar PV, dubbed ‘Ibri II Solar IPP’, is already well underway. An award for the 500 MW capacity project, which will come up in Ibri in Al Dhahirah Governorat­e, is expected before the end of this year, with commercial operation set for 2021.

Further, in line with its commitment to procuring new renewables based capacity at yearly intervals, the competitiv­e process for the third in the series of solar IPP projects will commence towards the end of 2019, with commercial operation envisioned in 2023. “This project may also have installed capacity of 500 MW or more, subject to our site and market evaluation­s,” said OPWP.

Significan­tly, two wind-based IPPS are envisioned for developmen­t as part of the current 7-year capacity procuremen­t cycle. The procuremen­t process is expected to commence towards the end of 2019 with commercial operation targeted during 2023. “The expected locations are in Duqm and Dhofar, and their installed capacities are expected to be in the range of 150 MW to 200 MW each,” according to OPWP. Oman’s government has stipulated a 10 per cent share from renewables in the country’s total generation portfolio by 2025.

 ??  ?? CEOS of Nama Holding and Group subsidiari­es pictured at the Annual Media Briefing yesterday. Photo: Khalfan al Toobi
CEOS of Nama Holding and Group subsidiari­es pictured at the Annual Media Briefing yesterday. Photo: Khalfan al Toobi

Newspapers in English

Newspapers from Oman