Oman Daily Observer

Sohar-3 kicks off final tests to start commercial operations in Q1 2019

- BUSINESS REPORTER MUSCAT, OCT 20

Shinas Generating Company SAOC (SGC), the developing company of Sohar-3 Power Plant, has announced Q1 of 2019 to commence commercial operations. SGC is targeting the third quarter of next year to be listed at Muscat Securities Market (MSM).

In 2016, the consortium of Mitsui & Co Ltd holding 50.1 per cent of the shares, ACWA Power and Dhofar Internatio­nal Developmen­t & Investment Holding Company (DIDIC) with 44.9 per cent and 5 per cent respective­ly, bagged the contract from the government to develop Sohar-3 Power Plant.

“The project is the second largest Power Plant in Oman with a net capacity of 1,710 megawatts”, Eng Abdullah Ali al Nofli (pictured), CEO SGC, said. He added that the work progress in the plant has reached a very advanced stage after completing the constructi­on work, and commencing the commission­ing and testing phase.

The plant — strategica­lly located at the Port of Sohar — is connected to a new constructe­d power transmissi­on network with a capacity of 400 kv, which contribute­s to the commercial and industrial boom in Al Batinah North Governorat­e and the entire country.

“With total investment­s of $ 957 million (approximat­ely RO 368 million), SGC’S role does not stop at the economic growth level of the country, but extends to the environmen­tal level through the company’s commitment to all safety systems, rules and regulation­s to preserve the environmen­t.

The company also committed towards In-country Value approach and accordingl­y allocated more than 21.6 per cent of the total constructi­on contracts value, amounting for RO 65.4 million to local companies”, Al Nofli said. The company is also committed to provide training opportunit­ies to Omani students and graduates.

Sohar-3 Power Plant operates on high efficiency basis using the latest technologi­es with a natural gas-fired combined cycle power plant, a system that reduces costs and increases the efficiency of the consumptio­n of natural gas used in generating electricit­y, thereby raising the efficiency in operation and produce low cost electricit­y to government.

Shinas Generating Company (SGC) was establishe­d in 2016 after the consortium of Mitsui & Co Ltd, ACWA Power and Dhofar Internatio­nal Developmen­t & Investment Holding Company (DIDIC) and signed Power Purchase Agreement (PPA) with state-owned Oman Power and Water Procuremen­t Company (OPWP) on March 1, 2016. Under the PPA, the consortium builds, owns and operates the power plant and sell power to OPWP for a period of 15 years from 2019.

Al Nofli said the plant will commence its commercial operations in the first quarter of 2019. Later that year, the company will present an attractive investment opportunit­y — in the light of pre-existing long term agreement with OPWP — by offering 40 per cent of its shares in a planned Initial Public Offering in the third quarter of 2019.

 ??  ??