Times of Oman

Raeco signs major power purchase agreement with OPWP to build Dhofar wind project

- A E JAMES

MUSCAT: Two agreements linked to the developmen­t of a planned 50 megawatt-capacity Dhofar wind power project, which will generate electricit­y needed for 16,000 homes, were signed by the Rural Areas Electricit­y Company (Raeco) here on Tuesday.

The power purchase agreement was signed by Raeco with Oman Power and Water Procuremen­t Company (OPWP), while another power connection pact was signed between Raeco and Oman Electricit­y Transmissi­on Company (OETC). The pact was signed by Eng. Saleh bin Nasser Al Rumhi, chief executive officer of Raeco, with Yaqoob Al Kiyumi, CEO of OPWP and Eng Masood Al Riyami, COO of OETC.

Abu Dhabi’s renewable energy company, Masdar, earlier signed an engineerin­g, procuremen­t and constructi­on ( EPC) contract with a global consortium comprising GE and Spain’s TSK to build the Dhofar Wind Power Project, the first large-scale wind farm in Oman and the GCC.

Joint developmen­t

The Dhofar Wind Power Project is a result of the joint developmen­t agreement that was establishe­d in 2014 between Masdar and Raeco. The wind mill will be located in Fattehit area in Shalem and Halaniyat Islands in Dhofar governorat­e. The $105 million capital expenditur­e of the project will be brought in by Masdar.

Eng Al Rumhi said that Dhofar Wind Power project is significan­t step in clean energy ventures in the region. “It is the first project of its kind in the Gulf region, which will be built in a total area of 1,900 hectares,” he added. He said that the wind power project will help avoid about 110,000 tonnes of carbon emissions per year when compared to fossil fuels, and it will enhance skills of Omani nationals by training them to work in such vital projects.

Expansion plans

Eng. Al Rumhi said that the company has reserved a large area for doubling the power generation capacity of the wind project. “We can double the capacity.”

GE will lead the EPC consortium, and will provide the project’s 13 wind turbines powered by the company’s latest 3.8MW wind turbine generator solution.

Rising demand

Eng Al Rumhi added that the demand for electricit­y grew rapidly in the recent past, which was in line with economic developmen­t. Accordingl­y, power supply in 2016 reached 30.4 terawatt hours, which was 5 per cent more than the average in 2015.

The Raeco chief said that the number of customers have increased by 7.4 per cent to 1,074,597 in 2016, compared to 2015. Therefore, the power producers, including Raeco, are looking for alternativ­e options to meet the growing demand.

He also noted that Raeco is looking at the possibilit­y of setting up renewable energy projects in 11 locations and feasibilit­y studies are going on. “At the end of this year or early next year, we will conclude the studies.” These projects could be solar, wind or hybrid projects.

“We are focusing on improving efficiency to optimise generation, other energy sources and interconne­ction with nearby areas.”

 ?? - Shabin E/ Times of Oman ?? RENEWABLE ENERGY: The wind project will be located in Fattehit area in Shalem and Halaniyat Islands in Dhofar governorat­e.
- Shabin E/ Times of Oman RENEWABLE ENERGY: The wind project will be located in Fattehit area in Shalem and Halaniyat Islands in Dhofar governorat­e.