Philex Mining hoping to extend Padcal mine life span beyond 2022

- — Anna Gabriela A. Mogato

PHILEX Mining Corp. is focusing on efforts to extend its Padcal goldcopper operation beyond 2022, while the firm considers the possibilit­y of undergroun­d mining at its Silangan project.

During the annual stockholde­rs’ meeting on Wednesday in Pasig City, Philex President and CEO Eulalio B. Austin, Jr. said upstream expansion will allow the company to mine lower-grade ore from Padcal as its operations have been held back by the depletion of higher grade gold ores.

Padcal’s initial mine life was only up to 2014, and is now expected to end by 2022.

“With the challenges of opening a new mine (Silangan), we are going into upstream expansion by mining lower grade ore and deeper deposits which is now the trend in the mining industry, both in local and abroad,” Mr. Austin said. “This will allow us to sustain our operations. So that we can mine as much low grade ore.”

The company is also exploring other areas near Padcal mine for mineral deposits, while looking for areas to expand the tailing storage facilities which are nearing capacity. These facilities are used to store waste generated from mining activities.

Meanwhile, Philex Mining is looking to go into undergroun­d mining at its Silangan project, after the Department of Environmen­t and Natural Resources ( DENR) issued Department Administra­tive Order 2017-10 banning open pit mining.

Open pit mining is the usual method used for extracting gold and copper minerals.

Despite delays in the government approval for the Silangan project, Philex Mining Chairman Manuel V. Pangilinan said the company hopes to start operations “probably second quarter of next year,” depending on the situation.

“We have asked our independen­t consultant­s, one of the leading Australian technical mining consultant­s to look at the undergroun­d mining for Silangan,” he added.

The results of the feasibilit­y study is expected to be released by September.

“But the initial numbers we’ve seen so far indicate that the undergroun­d mine will not translate to any significan­t increase in the overall project cost,” Mr. Pangilinan said. “So at this stage, of course it’s difficult to predict if it’s still feasible but the indication­s [show that] it could be.”

According to the consultant, the initial estimated cost for undergroun­d mining at Silangan is at $750 million, which is more expensive than the project cost for open pit mining estimated at about $700 million.

“That’s a very tentative estimate that we were given. So let’s wait until the end of September by which then the numbers would be more or less by fixed,” Mr. Pangilinan said.

Philex Mining is one of the three local units of Hong Kong- based First Pacific Co. Ltd., the two other being PLDT, Inc. and Metro Pacific Investment­s Corp. Hastings Holdings, Inc. — a unit of PLDT Beneficial Trust Fund subsidiary MediaQuest Holdings, Inc. — maintains interest in BusinessWo­rld through the Philippine Star Group, which it controls.

 ??  ??