LRMC counts cost of delay in gov’t approval of LRT-1 fare increase

- Valdez Denise A.

LIGHT RAIL Manila Corp. (LRMC), the private operator of the Light Rail Transit Line 1 (LRT-1), said it has incurred a “fare deficit” of about P100 million for the three quarters of 2018 due to the government’s delay in granting its fare hike petition.

“Our agreement calls for compensati­on of the… If the fares are at a certain level and it’s not raised, it’s in our agreement, what we call a ‘fare deficit’… (For 2018), there’s a P100 million difference in the revenue that we should have been getting with the increased fares versus what we got,” LRMC President and Chief Executive Officer Juan F. Alfonso told reporters on Friday.

LRMC applied for a P5 to P7 increase in LRT-1 fares last March — the second time it did since the company was awarded the contract to operate the train line in 2014. The Department of Transporta­tion (DoTr) has yet to approve the petition.

The consortium of Ayala Corp., Metro Pacific Light Rail Corp., Metro Pacific Investment­s Corp. (MPIC) and Macquarie Infrastruc­ture Holdings (Philippine­s) Pte. Ltd. started operating LRT-1 in September 2015, after it signed the P65 billion, 32-year concession agreement with the government in Oct. 2014. Based on the terms, LRMC is allowed to raise LRT-1 fares every two years.

The DoTr said in August LRMC’s petition was still under discussion, and would require a public hearing, before being approved.

Mr. Alfonso said even with the delays, the government has not paid for the fare deficits from the past years.

“We haven’t been compensate­d for fare deficits,” he said. “The mechanism in the agreement is for fare deficit or for fare increase. For fare increase, it is paid per user. So if I live in Manila, Makati or Pasay and I use the system, I pay for it. For fare deficit, then it’s taken… from DoTr (budget),” he explained.

Despite this, Mr. Alfonso noted LRMC is still making “a little bit of money,” but just enough to keep the system running.

LRMC allocated a capital expenditur­e of P7.5 billion for the rehabilita­tion of the train system, structural rectificat­ion and an extension of the line to Cavite.

Mr. Alfonso said they have already spent about P12 billion as of end-November. The capex budget is expected to shift starting next year to focus on the Cavite extension.

He said constructi­on of the LRT-1 Cavite extension is expected to commence by first half of 2019, as substantia­l right of way was already granted for the first of three segments of the extension.

The 11.7-kilometer extension that will build eight new stations from Baclaran to Bacoor, Cavite is seen completed by late 2021 or early 2022. Mr. Alfonso said the difficulty in relocating posts of Manila Electric Company (Meralco) was the cause of delay.

“We’re still assuming the same costs… Later on, if some of these things have delays and increased costs, then there’s a mechanism in our agreement to deal with it… There’s going to be escalation­s in costs,” he added.

MPIC is one of three Philippine subsidiari­es of Hong Kong’s First Pacific Co. Ltd., the others being PLDT, Inc. and Philex Mining Corp. Hastings Holdings, Inc., a unit of PLDT Beneficial Trust Fund subsidiary MediaQuest Holdings, Inc., maintains an interest in BusinessWo­rld through the Philippine Star Group. —

 ??  ?? FARES of Light Rail Transit Line 1 will increase once government approves Light Rail Manila Corp.’s petition.
FARES of Light Rail Transit Line 1 will increase once government approves Light Rail Manila Corp.’s petition.

Newspapers in English

Newspapers from Philippines