Business World

ERC approves EDC applicatio­n to link geothermal plant to Mindanao grid

- Victor V. Saulon

THE Energy Regulatory Commission (ERC) has approved the applicatio­n of Energy Developmen­t Corp. (EDC) to develop a point-to-point power transmissi­on line that will connect its 3.6-megawatt (MW) power plant near Mount Apo to the Mindanao grid.

However, the regulator denied the company’s applicatio­n to operate and maintain the transmissi­on line, a function which it gave to privately-owned National Grid Corp. of the Philippine­s (NGCP).

In arriving at its decision, the ERC said it had focused its evaluation on the technical capability of EDC to develop the transmissi­on facility, and the mode of recovery of cost in case it is “required for competitiv­e purposes and ownership” to be transferre­d to the government or NCGP.

In its decision, the ERC said that as a general rule state-led National Transmissi­on Corp. or its concession­aire NGCP has the responsibi­lity to provide grid interconne­ction for power generation facilities under Republic Act No. 9136 or the Electric Power Industry Reform Act of 2001.

However, the regulator pointed out an exception.

“A generation company may develop and own or operate dedicated point-topoint limited transmissi­on facilities that are consistent with the Transmissi­on Developmen­t Plan (TDP): Provided, that such facilities are required only for the purpose of connecting to the transmissi­on system, and are used solely by the generating facility, subject to prior authorizat­ion by the (ERC),” the agency said.

The ERC also said that the power plant was included in the committed projects submitted to the Department of Energy to help augment the power requiremen­ts of the Mindanao grid.

“Thus, the developmen­t of the subject facilities is necessary for the said connection,” it said.

In its filing, EDC placed the cost of the transmissi­on facility at P244.69 million. It intends to connect the plant to the grid through an approximat­ely 1-kilometer 69-kilovolt transmissi­on line.

EDC’s project, called Mindanao 3 (M3) binary geothermal power plant, expands its existing Mt. Apo geothermal facility with an additional supply of renewable power in Mindanao.

In its website, the company said the project will not only contribute reliable power to Mindanao but will also avoid around 25,000 tons of equivalent carbon dioxide yearly through the use of geothermal energy instead of coal.

The binary power plant, which started constructi­on during the pandemic, will make use of existing brine from the company’s 103-MW Mindanao 1 and 2 geothermal power plants to generate energy without need for additional drilling.

The brine’s heat is harnessed to generate electricit­y for the new power plant before it is re-injected back to the reservoir. It was synchroniz­ed to the Mindanao grid on March 12, 2022, and passed NGCP’s compliance testing on March 25. —

Newspapers in English

Newspapers from Philippines