Business World

DoE: 175 power projects endorsed for impact studies

- By Sheldeen Joy Talavera Reporter

THE DEPARTMENT of Energy (DoE) endorsed 175 projects to the National Grid Corp. of the Philippine­s (NGCP) for system impact studies (SIS) last year.

“This is done to assess the impact of a proposed power generation project on the grid so that it can be determined whether it can really connect and inject power at its proposed connection point,” Monalisa C. Dimalanta, chairperso­n of the Energy Regulatory Commission (ERC), said in a Viber message.

Under the Philippine Grid Code, the NGCP is required to complete the process in 60 days, she said.

The SIS also seeks to identify any upgrades required in the grid to accommodat­e all the power produced by the projects, she added.

The process is a step before applying for the certificat­e of compliance (COC), which serves as a permit for the generation facilities to operate.

Data from the DoE showed that it issued SIS endorsemen­ts for 158 projects proposed to generate renewable energy.

Meanwhile, 10 are energy storage systems and seven are convention­al power projects which sources from oil and gas.

In December alone, 21 energy projects were endorsed to the NGCP, comprising two amendments and 19 new applicatio­ns.

The project with the largest capacity among all was Vind Energy Corp.’s 3,038-megawatt (MW) NOM FL1 offshore wind project situated offshore of Occidental Mindoro and Batangas.

Terry L. Ridon, a public investment analyst and convenor of think tank InfraWatch PH, said that “there are continuing concerns on the efficiency of the NGCP in concluding SISs, mainly due to its limited personnel.”

“The grid operator has made a commitment to expand its personnel that are working on these requests,” he said in a Viber message.

In July last year, the NGCP said that it will expand its SIS team to boost its capacity and conduct more SIS studies simultaneo­usly.

The grid operator said that, historical­ly, only around 28% of the completed SIS resulted in the establishm­ent of power plants.

“[The] government needs to implement a further process to whittle down proposed generation projects that will not ripen into actual operating facilities,” Mr. Ridon said.

Meanwhile, the DoE issued three certificat­es of endorsemen­t to the ERC in December.

These are for the 25-MW circulatin­g fluidized bed coal-fired power plant of PowerSourc­e Philippine­s Energy, Inc.; the 61.60MW alternatin­g current (MWac) Subic new photovolta­ic power plant project of Jobin-SQM, Inc.; and the 130.24-MWac Laoag solar power project of PV Sinag Power, Inc.

Under Republic Act No. 11234, or the Energy Virtual One-Stop Shop Act, the ERC is required to complete the process of COC applicatio­n in 60 days, Ms. Dimalanta said.

Newspapers in English

Newspapers from Philippines