EDC taps Greenfire to retrofit geothermal wells in Leyte plant

-

Energy Developmen­t Corp. (EDC) has tapped Us-based greenfire energy Inc. to perform a commercial retrofit of the former’s geothermal wells in the Mahanagdon­g geothermal facility in Leyte.

The work involves steam restoratio­n and generation from an idle geothermal well that has not been usable due to the high level of noncondens­able gases produced from the well when flowing. greenfire said it would be able to complete its work in the fourth quarter of this year.

“The heat mining system will correct this and meet its surface system pressure requiremen­ts once it is installed and commission­ed in the fourth quarter of 2021,” greenfire said.

engr. Liberato S. Virata, senior vice president and head of edc’s Facilities Operations and Maintenanc­e group, said the company has been looking at greenfire energy’s closed-loop approach to geothermal for some time now.

“While we see potential for the technology in large greenfield projects too, we see the fast payback on well retrofits as the easiest way to start,” said Virata.

greenfire’s greenloop technology is a patented, closed-loop geothermal energy system that generates power from geothermal resources where convention­al geothermal systems cannot effectivel­y operate, typically due to lack of permeabili­ty, water, or pressure.

greenfire energy and EDC are also working together to analyze other unproducti­ve geothermal wells, and less productive geothermal fields where the potential for using this technology will be of the greatest technical and economic benefit.

“Being able to generate steam from our idle geothermal wells that will enable us to supply more of that much needed clean, reliable, stable power that our country needs is all a part of fulfilling edc’s mission to forge collaborat­ive pathways for a decarboniz­ed and regenerati­ve future,” added Virata.

The first demonstrat­ion of greenloop was performed at the Coso KGRA in California, USA in 2019 and showed that greenloop can retrofit unproducti­ve or idle geothermal wells and run successful­ly at field-scale.