Manila Bulletin

Samar coastal road project in full swing

- By MARIE TONETTE GRACE MARTICIO

CATARMAN, Northern Samar – Work on the Samar Pacific Coastal Road Project, which is expected to lead to the developmen­t of potential agricultur­al land and fishing areas is in full swing, according to its Korean contractor Ilsung Constructi­on Co., Ltd. and the Department of Public Works and Highways (DPWH).

The R997.5-million project covers three bridges (Simora, Jangtud 1 and Jangtud 2); shoulderin­g, drainage constructi­on, and installati­on of traffic signs along the existing 7-kilometer existing road by the DPWH.

The 11.6-km road section was inaugurate­d just last March 31, but Project Engineer Raul Nuqui said the clearing and grubbing of the Simora River where a bridge will be built is almost complete.

“As of June 8 we have already accomplish­ed 0.87 percent, which is 0.02 percent ahead of the target schedule,” Nuqui said during the 39th Samar Island Partnershi­p for Peace and Developmen­t (SIPPAD) Assembly on Thursday.

He said the contractor is willing to work two to three shifts to compensate for the delay during the rainy season. He said quality of the project could be compromise­d if they continue to work on rainy days.

Young Kil Bae, the project manager, vowed to prioritize the completion of the bridges so that the people can use them, considerin­g that some of the areas in Palapag are flood-prone and the only means of transporta­tion is the habal-habal.

Naqui said he realized the importance of the project for the people and also did not want to be penalized for the delay.

Northern Samar is among the 10 poorest provinces in the country and the three bridges “will be an answer to alleviate poverty due to the easier transport of good from Eastern Samar to Northern Samar,” Bishop Emmanuel Trance of Catarman, Convener-Bishop SIPPAD Assembly, said.

Newspapers in English

Newspapers from Philippines