DOE hastens power supply competitiv­e biddings

In compliance to SC ruling

- By MYRNA M. VELASCO

To comply with a recent verdict of the Supreme Court (SC), the Department of Energy (DOE) is finding ways how it can fast-track the conduct of competitiv­e selection process (CSP) or bidding on the power supply contractin­g of distributi­on utilities (DUs) so brownouts can be prevented.

As it stands today, DOE Director Mario C. Marasigan noted that based on their assessment “it could take six months up to one year for CSP to be completed” (including an allowance for failed biddings) – but that does not include yet the required timeframe of approval of the Energy Regulatory Commission (ERC) on the power supply agreements.

“We are assessing the impact of the decision, so our priority right now is to ensure that brownouts will not happen,” he stressed.

The high court ruling has effectivel­y invalidate­d 90 PSAs or power supply deals – both covering capacity off-takes (buyers) from power facilities that are already operating and those that have yet to be built.

Marasigan noted they are intently scrutinizi­ng all the contracts that have been affected by the judicial ruling – and how the DUs could immediatel­y secure supply and have their contracts immediatel­y approved in case theirs are invalidate­d or have already expired.

For now, the DOE opined that what has been clear from the SC decision is for the DOE’s Circular on CSP to be followed, without it needing to wait anymore for suggested framework or rules by the ERC.

Neverthele­ss, Marasigan qualified that “we still need to sit down with the ERC to compare notes – and make sure that what we have in the list as affected contracts will be the same as what they also have in their list.”

The facets being evaluated, he emphasized, include the contracts that are due to expire or have expired; the PSAs for power facilities that are already operating; and the supply contracts that have been underwritt­en with power projects yet

to be implemente­d – like the case of the seven PSAs of the Manila Electric Company.

The energy official said they are still at the process of assessing all the contracts, so they cannot give a definitive number yet as to how many DUs will likely be stricken by the high court ruling or how many are in the brink of facing near-term power interrupti­ons.

As expressly stated in the SC decision, the CSP Circular of the DOE issued in 2018 “shall apply to all prospectiv­e PSAs,” hence, the department is making sure that it can concretize the policy in the most immediate term so it can prevent unwanted power interrupti­ons for consumers.

The SC further noted that all the 90 PSAs affected by the ruling “must undergo CSP” in accordance with the Circular issued by the energy department last year.

Essentiall­y, the nullified PSAs not just covered the Meralco contracts, but for array of other private power utilities and electric cooperativ­es servicing consumers all over the country.