Manila Bulletin

Kaliwa Dam project done by 2026, MWSS says

- By JOE PRIELA

The ₱12.2-billion New Centennial Water Source Kaliwa Dam Project will be completed by mid-2026, and will be able to supply water to Metro Manila households and nearby areas by early 2027, the Metropolit­an Water Sewerage System (MWSS) said.

In a forum on Wednesday, Feb. 1, MWSS Administra­tor Leonor Cleofas said China Energy Engineerin­g Corporatio­n (CEEC), which is undertakin­g the project, has reported the overall project accomplish­ment at 21 percent.

“There are two major components of the project, which are the tunneling and the constructi­on of the dam. It has started with tunneling and it will be complete by the middle of 2026. At the same time, if the validation of the settlement of 46 families is accomplish­ed, the dam will also begin and MWSS is endeavorin­g to complete the dam by 2026,” Cleofas said.

The Kaliwa Dam project is a 63-meter-high reservoir that will hold an initial discharge capacity of 600 million liters per day, intended to supply Metro Manila, as well as nearby areas that only depend on two dams in Bulacan.

A Tunnel Boring Machine (TBM) is being used for the 28-kilometer-long conveyance tunnel that will stretch from Teresa Rizal to General Nakar, Quezon Province. It will pass through Barangay Magsaysay in Infanta, Quezon as well as several barangays in Baras, Morong, Tanay, and Teresa towns in Rizal. At its deepest, the TBM will be 500 meters below the Sierra Madre Mountains.

The excavation at the tunnel outlet in Teresa started on Dec. 7 last year.

MWSS said the National Commission on Indigenous Peoples (NCIP) already issued a Certificat­ion Preconditi­on.

In September last year, MWSS got the approval of the Department of Environmen­tal and Natural ResourcesP­rotected Area Management Board (DENR-PAMB) for clearances as prerequisi­te for a Special-Use Agreement on Protected Areas.

The constructi­on of the dam was put on hold last year due to the protest of the indigenous peoples (IPs) in the area, particular­ly the DumagatRem­ontado communitie­s in Rizal and Quezon provinces, who asserted that the dam will be encroachin­g on their ancestral land.

The project will also be passing through three watershed areas.

MWSS said that it has forged mutually beneficial agreements with IPs, local government units, and the DENR to meet all explicit conditions under the environmen­tal compliance certificat­e, laying a groundwork for enduring relationsh­ips with the communitie­s.

A comprehens­ive and inclusive socio-economic developmen­t plant was developed to ensure that those who are going to be affected by the project can participat­e and contribute to the developmen­t of their communitie­s.

Newspapers in English

Newspapers from Philippines