Manila Standard

1,200-MW Sual coal plant resumes operations after weekend maintenanc­e shutdown

- Alena Mae S. Flores

THE Department of Energy said Monday the 1,200 megawatt Sual coal-fired power plant is now back in operation after undergoing maintenanc­e shutdown over the weekend.

It said the Sual coal plant underwent maintenanc­e from April 29 to May 1 to conduct repairs.

“Concerns with Sual units 1 and 2 were resolved and both are operating as planned. Sual unit 2 is fully operationa­l, while unit 1 is maintained [at] max level of 580 MW until further repair and maintenanc­e activities are done by June or July,” Energy assistant secretary Mario Marasigan said.

The grid operator did not place the Luzon grid on red or yellow alert despite the maintenanc­e shutdown because of low demand over the weekend.

The Sual plant had to resolve the buildup of a leak from the boiler tube and clean the generator stator lot bar to rectify the increase in temperatur­e.

Energy officials said, however, that if they allowed plant to conduct the maintenanc­e for seven-days on May 5 to 11 as requested, it would result in a possible yellow alert, or worst, red alert on Week 18 (May 1 to 7) and Week 19 (May 8 to 14).

This was agreed during the assessment meeting among the DOE team, National Grid Corp. of the Philippine­s and TeaM Sual Corp. on April 25.

The DOE received a notice from the TSC on April 24 requesting to undergo unplanned maintenanc­e of its Sual Unit 1 on May 5 to 11.

The DOE also asked for the public’s cooperatio­n by rationaliz­ing the use of power during the peak demand hours of 11:00 a.m. to 12 noon, 2 p.m. to 3 p.m. and 6 p.m. to 7 p.m. to mitigate the impact of the maintenanc­e shutdown.

It encouraged all offices and residences using air conditione­rs to set their thermostat at 25 degrees Celsius during these times.

Newspapers in English

Newspapers from Philippines