Dec. 15 deadline set for 600 temporary shelters in Marawi

1,200 houses being built on 11-hectare land for residents displaced by war on Islamic State

- —DIVINA SUSON AND RICHEL UMEL INQ

MARAWI CITY— A multiagenc­y government team in charge of rebuilding parts of the city flattened by the war between terrorists and government forces had given itself until Dec. 15 to finish up to 600 temporary shelters for displaced residents.

The government aims to build 1,200 temporary shelters on an 11-hectare land about 3 kilometers from the city center.

Felix Castro Jr., housing assistant secretary and Task Force Bangon Marawi (TBFM) field officer, said his team was confident of meeting its deadline despite erratic weather in the city.

Five contractor­s

Five contractor­s were simultaneo­usly building prefab houses under the supervisio­n of the National Housing Authority. The Department of Public Works and Highways (DPWH) was building or repairing roads, preparing the housing site, landscapin­g and digging foundation holes.

Heavy equipment from DPWH provincial engineerin­g districts in Mindanao had been deployed to the housing site to finish a road network by Nov. 25.

While there were delays because of the weather, Castro expressed confidence workers would meet the projects’ deadline.

One worker, however, said one of the reasons for the delay was lack of manpower. There were also delays in transport of materials, said the worker, who asked that he not be identified.

Unpaid land

Omarashari­ff Yassim, a DPWH engineer, said some lot owners also prevented work because they had not been paid.

Farmers who were bound to lose crops were demanding compensati­on, too, Yassim said.

But Castro said these problems would not prevent workers from meeting deadlines.

He said a comprehens­ive rehabilita­tion plan for Marawi was in the works.

The TFBM was facilitati­ng the return of families to nine villages cleared by the military of unexploded bombs.

The team was also ensuring there would be electricit­y and water supplies in these areas.

According to Castro, only three villages are still without water connection.

Free services

Nordjiana Ducol, Lanao del Sur Electric Cooperativ­e general manager, said power had been restored to 63 of 96 villages as of Nov. 9.

Ducol said restoratio­n of power supply to households was being done for free.

Petter Gelli, district head of Lanao del Sur 2nd engineerin­g office, said his office was ready to clear the main battle area of debris.

The task would be easier, he said, because China donated 47 pieces of heavy equipment.

Maria David, who is in charge of operations at the DPWH 2nd engineerin­g office, said clearing operations were a prelude to rehabilita­tion.

 ?? —JEOFFREY MAITEM ?? Many residents displaced by the Marawi war still receive relief goods from the government, checking if their names are on the list posted at a DSWDoffice.
—JEOFFREY MAITEM Many residents displaced by the Marawi war still receive relief goods from the government, checking if their names are on the list posted at a DSWDoffice.
 ?? —RICHEL V. UMEL ?? Some of the trucks and constructi­on equipment donated by China for rebuilding Marawi City.
—RICHEL V. UMEL Some of the trucks and constructi­on equipment donated by China for rebuilding Marawi City.