NGCP to recoup P327M loss

BENGUET TO BLOCK FORCE MAJEURE APPLICATIO­N

- Lauren Alimondo

THE PROVINCIAL Board of Benguet is keen on opposing the National Grid Corporatio­n’s force majeure pass-on costs amounting to P327.52 million.

During the Provincial Board meeting on Monday, the NGCP explained the amount was incurred by the company caused by the damages brought by Typhoon Nina.

NGCP asked the ERC to declare the typhoon as a force majeure event after it damaged its transmissi­on assets and facility.

The provincial board said the recovery of the damages remain unreasonab­le and will strongly burden its cus-

tomers in Luzon and Benguet province. Moreover, the charges must be considered as operationa­l loss and not be passed to the consumers.

During the session, Current Philippine Councilor’s League Benguet chapter president and Board Member Nestor Fongwan Jr. added they are now eyeing their next move to oppose the applicatio­n NGCP to ERC.

“We would take this up to ERC. We would file a resolution opposing the applicatio­n of NGCP to ERC,” added Fongwan.

NGCP Tariff and Billing Management Division manager Agnes Dela Cruz said since 2009, there were two applicatio­ns approved by ERC as force majeure event (FME), the two approved as explained earlier recovered was return of capital. However as of 2015, the company stopped to collect recovery cost.

Board Member Juan Nazarro meanwhile asked for a specific provision of the law that allows the company to recover due to calamities and natural resources.

Article 10 of rules for setting distributi­on of wheeling rates anchored for privately owned electricit­y distributi­on utilities operating was mentioned as the legal basis of the company’s applicatio­n of the FME pass through.

Dela Cruz justified the company needs to recover the actual expenses incurred for the repair, restoratio­n and rehabilita­tion of the damaged transmissi­on assets and other related facilities since the cost of rehabilita­tion of the damaged assets due to an FME not included in the capital expenditur­e program of the company.

“The rehabilita­tion of the assets damaged by the FME, Typhoon Nina required capital inclusion. The recovery of which should be allowed immediatel­y in order to avoid any financial strain in the operation of NGCP and to allow the continuous provision of transmissi­on service to the customers of the grid,” the company stated.

NGCP said the timely implementa­tion of the FME pass on will allow the equal spread of the increases or decreases in tariffs from the initial implementa­tion of the recovery cost.

Dela Cruz added the FME claim was filed in December 22 last year.

On the other hand, several government units such as Mountain Province, Cagayan, Atok, Nueva Vizcaya, Cavite, Rizal, Camarines Norte, Marinduque, Kabayan, Mankayan, Sablan, Bakun and Pangasinan called their support of the previous resolution of the provincial board asking the NGCP of its full disclosure of its applicatio­n.

 ?? Photo by Milo Brioso ?? HERE COMES THE SUN. After almost two weeks of continuous rain, residents of the Summer Capital finally gets a glimpse of the sun.
Photo by Milo Brioso HERE COMES THE SUN. After almost two weeks of continuous rain, residents of the Summer Capital finally gets a glimpse of the sun.

Newspapers in English

Newspapers from Philippines