GET READY, MANANGA BRIDGE 3 TO CLOSE SOON

-

Motorists who regularly travel on the Cebu South Coastal Road in Talisay City were urged to brace for “slight” traffic delays.

The City of Talisay Traffic Operations and Developmen­t Authority (CT-TODA) laid out a traffic scheme in preparatio­n for the rehabilita­tion and repair of the Mananga Bridge 3 on the Cebu South Coastal Road.

The Department of Public Works and Highways (DPWH) Second Engineerin­g District aims to start rehabilita­ting Mananga Bridge 3 on Friday, April 27.

Rehabilita­tion of the northbound lane of the bridge, for P29 million, could last until the second or third week of June, said DPWH Second Engineerin­g District head Leslie Anthony Molina.

Engr. Almond Dela Peña, CT-TODA head, said that even after DPWH’s contractor starts work on Friday night, three lanes of the Mananga Bridge 3 will remain open.

Two lanes will be open to motorists going to Cebu City while one lane will be open to southbound traffic from 6 a.m. to 12 noon.

From noon to 10 p.m., the CT-TODA will then open two lanes for those traveling to the south and one for those going to Cebu City, Dela Peña said.

Traffic enforcers from CT-TODA will be deployed on both ends of the bridge to prevent traffic congestion.

‘Slight congestion’

Dela Peña pointed out there are alternativ­e routes for motorists in case they want to avoid traffic on the CSCR. Motorists can use the alternativ­e routes from Barangay Tabunok to Rabaya St. and Fidel Bas St. to San Isidro Road.

There’s also a diversion road from Barangay Linao but due to an ongoing road rehabilita­tion there, motorists are not advised to use it, for now.

Dela Peña expects “slight congestion” near the Mananga Bridge 3 since the rehabilita­tion was timed for the summer vacation, when fewer trips are made daily.

The traffic scheme aims to minimize trip delays, especially during rush hour, Dela Peña added.

In a separate interview, Molina said that after coordinati­ng with CTTODA, the DPWH started placing signs from Talisay City to Cebu City to inform motorists about the rehabilita­tion and repair works.

Molina also assured the public that their contractor will work 24 hours daily to ensure that their work on the Mananga Bridge 3 will be finished in June.

“We will closely monitor the contractor to ensure that they don’t delay the repair of the bridge,” Molina added.

 ?? SUNSTAR FOTO / ALLAN CUIZON ?? TIME FOR REHAB. Starting on Friday, April 27, the northbound lane of Mananga Bridge 3 will be closed for rehabilita­tion. The public works department expects this situation could last until the middle of June.
SUNSTAR FOTO / ALLAN CUIZON TIME FOR REHAB. Starting on Friday, April 27, the northbound lane of Mananga Bridge 3 will be closed for rehabilita­tion. The public works department expects this situation could last until the middle of June.