Sun.Star Cebu

Changes will make CCMC better, officials assure

- /RVC

Some major changes in the structural design of the Cebu City Medical Center (CCMC), including the number of floors, will be implemente­d by the Cebu City Government to produce a better hospital.

In a letter to then acting city engineer Josefa Ylanan, Hospital Administra­tor Kenneth Siasar said that adjustment­s have to be done, not only in the room configurat­ions, sizes and, assignment­s by floor, but also the types of flooring, walls, and ceiling finishes.

“Following the temporary reduction of the number of floors from 10 floors to 7 floors, because of budget constraint­s at this time, the location assignment and adjustment of the different rooms and facilities of the entire project need to be revised and adjusted to conform to the reduced number of beds, but still confirming to the existing DOH requiremen­ts,” reads a portion of the letter.

Siasar said in the latter that the changes had to be addressed as soon as possible. “In order not to waste scant government resources, works and partitions… have to be suspended until (some specificat­ions) are finalized and approved by us, the users.”

The letter was dated April 6, 2018 and noted by Councilor Mary Ann delos Santos, who serves as deputy mayor for health services.

The same letter was also posted by Mayor Tomas Osmeña in his Facebook page to clarify that work on the CCMC project was not suspended.

Major variations

However, in a memorandum dated April 6, Osmeña temporaril­y suspended work on the CCMC but did not specify what part of the project would be affected.

“The CCMC intends to initiate major variations in the scope of the contract during its implementa­tion to suit changes in physical conditions of the hospital to conform to the existing requiremen­ts of the DOH,” reads a portion of the memorandum.

In a text message last Friday, Councilor delos Santos explained that from a 10-storey building in the original plan for the CCMC project, the facility will be six floors instead.

Because of the changes, the number of beds to comply with DOH’s requiremen­ts for a tertiary hospital also has to be adjusted, delos Santos said.

“Some private rooms will be converted to wards to accommodat­e more patients. There will be a total of 219 beds, which would still be compliant at the tertiary level,” she told SunStar Cebu.

Not done today

A tertiary hospital needs to have 150 to 200 beds, the councilor said.

Meanwhile, following the issuance of show-cause order, the Department of Engineerin­g and Public Works DEPW will have to evaluate the contractor’s explanatio­n for why work on the project was delayed.

Engr. Kenneth Enriquez said that the delay incurred in the civil works of the project is already a ground to terminate the contract between the two parties.

As of March this year, C.E. Padilla Constructi­on Inc., the contractor of the project, had incurred a -23 percent slippage, which means that they were behind schedule.

The target completion date for Phase 1 of the new CMMC was supposed to be today, May 27.

“They have to explain the delay and we will also refer the matter to the City Legal Office because they have a contract with the City,” Enriquez said.

 ?? SUNSTAR FOTO / AMPER CAMPAÑA ?? LET’S GET MOVING. Cebu City Hall’s Department of Engineerin­g and Public Works will ask its contractor to explain why work on the Cebu City Medical Center on N. Bacalso Ave. is behind schedule.
SUNSTAR FOTO / AMPER CAMPAÑA LET’S GET MOVING. Cebu City Hall’s Department of Engineerin­g and Public Works will ask its contractor to explain why work on the Cebu City Medical Center on N. Bacalso Ave. is behind schedule.

Newspapers in English

Newspapers from Philippines