After 2 years of congesting traffic. bridge to be finished by mid-June

- By Bomie Lane S. Castillo

THE Davao River Bridge widening project of the Department of Works and Highways Davao Region (DPWH 11) connecting Ma-a and Buhangin along the Carlos P. Garcia Highway (Diversion Road) will finally be completed by second week of June this year, two years since it started and has been causing daily traffic pile-up.

At least that is what DPWH 11 Chief Informatio­n Officer Dean Ortiz said in an interview with Sun.Star Davao, saying the widening project took two years to complete due

to repeated soil collapse that required project plan revisions.

In an advisory released by DPWH Davao yesterday, May 23, the Davao River Bridge was temporaril­y closed to all motorists from midnight to 6 a.m. today, May 24, for the installati­on of girders or steel beams.

Ortiz said the installati­on was supposed to have been done last May 21, Sunday, but they had to cancel the constructi­on due to bad weather.

"We have already installed two girders last Sunday. So for tonight, we have to continue installing six more girders to complete the eight-girder requiremen­t," Ortiz said.

After the establishm­ent of girders, Ortiz added that they will immediatel­y continue with the road pavement as the last step of the widening project before its official completion this June.

He said they will be doing their best to avoid any technical and mechanical issues that may again cause delays.

The Davao City Transport and Traffic Management Office (CTTMO) has been assisting motorists on the alternativ­e routes available around Diversion road, but traffic pile-up continues as the alternativ­e routes are narrow and just as congested. BSC