Sun.Star Davao

BULK WATER PROJECT STILL IN FULL SWING

Despite setback, Apo Agua continues to target to supply water before yearend

- BY RALPH LAWRENCE G. LLEMIT

DESPITE the challenges caused by the Covid-19 pandemic, Apo Agua Infrastruc­tura Inc. (Apo Agua) is targeting to distribute potable water from the Davao City Bulk Water Supply Project (DCBWSP) to its consumers before the end of 2021.

Apo Agua Operations Head Shake Tuason told the media in a press conference that“uncertaint­ies” due to the pandemic, including the strict protocols imposed by the government such as the mandatory quarantine for workers, and the need to observe physical distancing in project sites, had caused a setback to the project.

“That has impacted the productivi­ty levels of our workforce,” Tuason said on Wednesday, April 14, during the AFP-PNP Press Conference.

He added that they are experienci­ng logistical constraint­s from suppliers due to the mobility restrictio­ns, resulting in difficulti­es and delays in the import of equipment and materials for the completion of their project.

Tuason also attributed the restrictio­ns imposed in the city during the enhanced community quarantine (ECQ) from April to mid-May in 2020, resulting in the temporary suspension of the constructi­on in abidance to the quarantine measure.

Tuason also cited the recent weather conditions. He, however, said they are still targeting to deliver the project as scheduled, and is constantly monitoring the current situation

“In terms of project progress, we’re very happy to report that constructi­on is in full swing. We have a [very] aggressive timeline for us to complete the project [and] for us to have the first drop of water by the end of this year,” Tuason said.

To fast-track the project, the official said they had to increase their manpower from 2,000 onsite workers during the pre-pandemic, to 4,500.

‘Comprehens­ive testing’

DCWD spokespers­on Jovana Cresta Duhaylungs­od said even if the infrastruc­ture project of the bulk water will be completed, she said there will be a series of comprehens­ive testing, evaluation, and integratio­n processes to be conducted.

“It doesn’t mean na paghuman ni Apo Agua, start dayon ta og distribute (that when Apo Agua finishes the constructi­on, we will immediatel­y start the distributi­on),” Duhaylungs­od said.

However, she said they will try to shorten the testing period to expedite the distributi­on of water to the consumers.

Duhaylungs­od said they are targeting to fast-track the project in order to start supplying areas with low or no running water supply and those that have deteriorat­ing water quality.

She added that the imposed quarantine restrictio­n had caused a high water consumptio­n resulting in some areas experienci­ng low water supply.

If ever the project will not meet its targeted operation, she said DCWD has reserved production wells as a mitigating measure that could cover the increase of water demand by 2022.

However, she said these wells might not be able to augment further, and that the bulk water must be completed soonest.

The project, worth P12.6 billion, is a strategic infrastruc­ture initiative that will shift the dependence of the city’s main water supply from groundwate­r wells to the more sustainabl­y-sourced surface water from Tamugan River. Once operationa­l, the DCBWSP will provide over 300 million liters of safe water per day to more than one million Dabawenyos.

Newspapers in English

Newspapers from Philippines