LGU appr oval of cell towers

-

It all started with President Duterte’s SONA. He warned all telecommun­ication companies (Telcos) to improve their services or be expropriat­ed by the government. The Telcos then responded by saying that it is the local government units (LGU) who are causing delays in the installati­on of cell tower s.

Following President Duterte’s order to to improve the digital infrastruc­ture in the country, the Department of the Interior and Local Government (DILG) announced that a joint memorandum circular of concerned agencies will be issued to streamline the documentar­y requiremen­ts and processing time for the building permits of the telecommun­ication towers. The processing time is a maximum of 20 days. In addition to streamlini­ng permitting requiremen­ts, the government also allowed the use of common cell tower s.

The DILG said there will be no more resolution­s from City or Municipal Councils and from homeowners associatio­n (HOA). To be secured are barangay clearance and other documentar­y requiremen­ts for building permit applicatio­ns on common towers such as Unified Applicatio­n Form for Locational Permit, Fire Safety Evaluation Certificat­e, building permit, property documents and select ancillary permit and accessory permits requiremen­ts.

It’s good that the Sanggunian Bayan/ Panlungsod is out of the picture because they will have a tough time complying with the 20 day deadline. The Sanggunian needs a minimum of two weeks to approve a resolution, unless a special session is called for the purpose. The first week is first reading and referral to the appropriat­e committee. Assuming the committee hearing goes without any problem, the resolution is approved the following session day.

Based on my experience as councilor, the delay in the approvalof­thecity/municipalc­ouncilisac­tuallytheT­elco’s compliance to the locational guidelines for base stations of cellular mobile telephone service of the HLURB. It requires among others a Barangay Resolution, consent of the HOA, Department of Health (DOH) report and the conversion of the land where the cell tower will be erected. There are instances when they submit incomplete requiremen­ts.

Under the HLURB guidelines, the approval of the HOA and residents whose property is adjacent to the base station is needed if the site is inside a subdivisio­n.

If there is no HOA, there should be a written consent of the majority of the actual occupants and owners of properties within a radial distance equivalent to the height of the base st at i on.

As for the DOH, the HLURB requires a Radiation Protection Evaluation Report from the Radiation Health Service.

If the land where the cell tower will be erected is agricultur­al, it has to be converted to non-agricultur­al use by the Department of Agrarian Reform. These two are the hardest to secure. It takes months to get them.

If the site is near an airport, a clearance from the Civil Aviation Authority of the Philippine­s is also needed.

Another cause of delay is opposition to the project.

issues of the residents/ homeowners.

First things first. The security set up has been strictly monitored mainly due to the threat of the COVID 19 pandemic. Visitors from other places were given limited access to the subdivisio­n in order to avoid local transmissi­on of the disease. Ditto with vehicle owners who do not have yet the FCTMCHAI stickers. They were methodical­ly advised to secure their stickers to avoid inconvenie­nce at the gate.

Next, the managing officers-President, Secretary and Treasurer, accompanie­d by Board member Emmanuel P. Limpin, worked hard to open up a new bank account. They were repeatedly told to come back and accomplish all the bank requiremen­ts. This way, all its bank transactio­ns will be handled hassle-free.

 ??  ??
 ??  ??