SCHEDULED SERVICE INTERRUPTIONS ON AUGUST 8-14, 2020
August 8, 2020
[1] Time: 10:00 A.M. to 4:00 P.M. (6hrs) Purpose: To help strengthen the distribution system of Brgy. Taptap from unwanted faults by conducting primary wire upgrading and replacement.
Areas affected: Portion of Cebu City (Taptap, Tagba-o
and Tabunan) along Sister Cities Drive and RM Drive including portions of Sitios Paling, Udlom, Batallon, Proper Tagba-o, Proper Taptap, Proper Tabunan, Lower Taptap, Awayan, San Miguel, Buanan, Tupas, Luyo, Caba-asan, Pung-ol Sibugay, Cantipla 1, and Acacia Proper. [2] Time: 9:00 A.M. to 11:00 A.M. (2hrs)
Purpose: To prevent unnecessary interruptions due to hotspot in the distribution system serving Tabok and Labogon, we will be conducting a replacement of damaged equipment and accessories.
Areas affected: Portion of Mandaue City (Tabok and
Labogon) along Tabok Highway and Cebu North Hagnaya Wharf Road, including portions of Basak, Tabok, Emperador & Raffles Warehouse, Hermag Village, and Bakilid.
[3] Time: 9:00 A.M. to 11:00 A.M. (2hrs) Purpose: To prevent unnecessary interruptions due to hotspot in the distribution system serving Alang-alang, Looc and Umapad, we will be conducting a replacement of damaged equipment and accessories.
Areas affected:
Portion of Mandaue City (Alang-alang, Looc
and Umapad) along Batiller St., Plaridel St., and Criston Road including portions of Purok Mango, Lemonsito and Bohol-Bohol.
August 9, 2020
[1] Time: 9:00 A.M. to 11:00 A.M. (2hrs)
Purpose: To prevent unnecessary interruptions due to hotspot in the distribution system serving Centro, Mandaue City, we will be conducting a replacement of damaged equipment and accessories. Areas affected: Portion of Mandaue City (Centro) along Burgos St., Don Andres Soriano Ave., including portions of Reclamation Area, Tribunal.
[2] Time: 9:00 A.M. to 11:00 A.M. (2hrs) Purpose: To prevent unnecessary interruptions due to hotspot in the distribution system serving Guadalupe, Lahug, Ce-bu City and Mohon, Talisay City, we will be conducting a replacement of damaged equipment and accessories.
Areas affected:
Portion of Cebu City (Guadalupe and Lahug)
and Talisay City (Mohon) including portions of Sitios Sunrise, Biasong, palm River Subd, Biasong, Rafael Homes, Sitio Ranger, Joanna Legacy Homes, Sitio Batoy, Zone 1 Biasong, Zone 4 Bi-asong, Zone 5 Biasong, Central Biasong, Pooc, Zone 2 Laguna, Biasong, Raphael Homes and Alea Subdivision Malibu. [3] Time: 8:00 A.M. to 4:00 P.M. (8hrs) Purpose: To conduct overhead line works near Paknaan Substation. It is in accordance with the plans for the Paknaan Substation Rehabilitation Project. This is an urgent undertaking for the rehabilitation of the Paknaan Substation to im-prove its service and make it more reliable.
Areas affected: Portion of Mandaue City (Tabok and
Labogon) along Cebu North Road, PC Suico St., J. Rizal St., Highway Tabok, High-way Paknaan including, North Road Labogon, portions of Lower Tabok, CTK Commercial Bldg., R.S Cabahug Warehouse, VNU Arcade 1 and Zone Okra. [4] Time: 6:00 A.M. to 12:00 P.M. (6hrs)
Purpose: To prevent unnecessary interruptions due to rotten pole and old wires in the distribution system serving Brgy Capitol Site by conducting pole replacement and relocation.
Areas affected:
Portion of Cebu City (Capitol Site) along Don Gil Garcia St., Adelfa St., LLorente St., Walingwaling St., and Azucena St., including portions of Don Mariano Cui, Chong Hua Medical Arts Bldg., Osmeña Avenue, Yap Bldg., and Ching Hua Hospital.
August 11, 2020
[1] Time: 9:00 A.M. to 1:00 P.M. (4hrs) Purpose: To increase the capacity of the distribution system serving Brgy North Poblacion, san Fernando by installing additional transformer. Areas affected: Portion of San Fernando, Cebu (North Poblacion) along Petra Pael St.
August 13, 2020
[1] Time: 8:00 A.M. to 4:00 P.M. (8hrs) Purpose: This is the 1st of 3 planned power outages to upgrade the reliability for the 23kV South Cluster. This project will create a backbone line within SRP complementing Don Gil Garcia and Talisay Substations which serves customers from Cebu City and Talisay City respectively. This is an urgent undertaking to minimize the impact of unplanned outages. Areas affected:
Portion of Cebu City (South Reclamation
Project) including portions of Bldg. 1 Amalfi Oasis Bldg., Bldg. 2 Amalfi Oasis Bldg., ABC Bldg., Kawit Amusement Park, South Reclamation Area, South Road Properties, E.R.M.M. Repair Bay, Building 6 San Remo, Sugbo Admin Bldg., Zone 2 Biasong, Talisay City and Amalfi City di Mari.