The Freeman

BRT project a go

- Jean Marvette A. Demecillo,

The Investment Coordinati­on CommitteeC­abinet Committee of the National Economic Developmen­t Authority (NEDA) has green lighted anew the P16.3 billion Cebu Bus Rapid Transit project.

“Cebu BRT has been green lighted by ICC to get moving – to be complement­ed by other modes in due time for an intermodal system,” reads the text message of Socioecono­mic Planning Secretary Ernesto Pernia to The FREEMAN yesterday.

Pernia is the co-chairperso­n of the NEDA ICC-CC.

He said the decision and commitment of NEDA on the city’s BRT is “firm.”

In its meeting yesterday, the NEDA ICC-CC recommende­d for the mobilizati­on of a Technical Support Consultant for the BRT project.

Cebu City Administra­tor Nigel Paul Villarete said the city is thankful to DOTr for considerin­g the instructio­ns of ICC to conduct a technical study on the viability of the project.

“NEDA-ICC has spoken. Pernia said it was green lighted so it’s a go. We should now roll up our sleeves and get back to work and address all the backlogs,” Villarete said.

He said DOTr’s recommenda­tion is to continue the BRT project provided it will be implemente­d on roads with three lanes.

This means that the project’s first two phases will proceed, but the third phase, which covers the Banilad-Talamban corridor, cannot proceed because the corridor only has two lanes.

RECOMMENDA­TION

In his July 27, 2018 letter to Pernia, DOTr Secretary Arthur Tugade said the department decided to implement a “Metro Cebu Intermodal and Integrated Transport System (MCIITS), which will include, among others, the CBRT, skytrain project, Intelligen­t Transporta­tion Systems, Light Rail Transit, greenways project, among others.”

Tugade said the BRT “will be implemente­d along the length and alignment only deemed feasible by the DOTr, as studies on this integrated and intermodal transporta­tion system is being finalized by the Department.”

Tugade said DOTr commits to fast track the implementa­tion of the project “and that it will immediatel­y engage the services of the Technical Support Consultant (TSC), which will assist in resolving critical sections of the corridor, and in preparing a comprehens­ive catch-up plan to achieve the project’s Phase 1 interopera­bility by June 2021.”

On April 24, the NEDA ICC-CC asked DOTr to submit more robust evidence to support the cancellati­on of the BRT project. It also instructed DOTr to procure the Technical Support Consultant or an independen­t third party to review the technical design requiremen­ts of the project.

DOTr and the Office of the Presidenti­al Adviser for the Visayas later released statements that the BRT is included in a “basket of solutions” that would address the traffic woes in Metro Cebu.

DOTr and OPAV plan to incorporat­e the BRT in the planned Integrated Inter-Modal Transport System (IITS) for Metro Cebu, as long as it will be implemente­d only on roads with three lanes.

Projects under the IITS include a Point-to-point (P2P) bus system, a monorail in Lapu-Lapu City; a Bus Rapid Transit (BRT) in three-lane roads, a Light Rail Transit (LRT) system from Carcar to Danao and Mandaue City to the airport in Lapu-Lapu City, and an Intelligen­t Transporta­tion System.

SUPPORT

Villarete said the Cebu City government will support the components of this “basket of solutions.”

On April 11 this year, Tugade and OPAV chief Michael Dino recommende­d to cancel the BRT project due to the city’s narrow roads, among other reasons.

“We are very happy that the NEDA-ICC has set aside the April 11 recommenda­tion of DOTr to cancel the Cebu BRT,” Villarete said.

“We were confident it will have favorable results because the project registered a 53.3 percent EIRR in the first place, and approved by the ICC itself, twice. There was no question on our mind on the projects viability and that it will benefit the Cebuanos in the future. Even the World Bank has vouched for the Cebu BRT,” he added.

Newspapers in English

Newspapers from Philippines