The Freeman

Irregulari­ties found

The Commission on Audit (COA) has found “indication­s of irregulari­ties” in procuremen­t and implementa­tion of projects in Cebu City.

- Caecent No-ot Magsumbol, Staff Member

According to COA’s report for 2021, these indication­s were found in the city’s solid waste disposal, in the completion of the Cebu City Medical Center (CCMC), and in the procuremen­t of rice allegedly from a non-illegible supplier in line with the city’s COVID-19 response, among others.

WASTE DISPOSAL

“Several indication­s of irregulari­ties were noted in the areas of (a) procuremen­t and (b) project implementa­tion of the solid waste disposal services totaling ₱383,531,706.00,” part of the observatio­n of COA‘s executive summary reads.

These have reportedly exposed the city to the risk of giving the impression that it favored a contractor, aside from the risk of attaining its program’s objective, COA said.

COA has recommende­d directing the Bids and Awards Committee (BAC) to submit the documents that are still lacking and to explain why a recommenda­tion for award to the Joint Venture of Docast

Constructi­on and the JJ and J Constructi­on and General Supply was proper despite the presence of “glaring grounds” that would disqualify them from the project.

“We also recommende­d for the submission of the machine-generated receipts of the weighbridg­e to validate the total number of tonnages paid by the City and an explanatio­n of the unusual pattern of change of the tare weights of the hauling equipment of the contractor,” COA said.

What are these grounds for disqualifi­cation?

COA noted that ownership and structure of the contractor did not agree with the city’s requiremen­t; the primary business of both contractor­s appeared to be constructi­on rather than logistics or hauling services, which was also not in accordance with the city’s TOR; and the bidder did not qualify in terms of the motor pool location requiremen­t.

COA also noted that the contractor started the hauling and management of the solid waste even though the post qualificat­ion was not yet started; and that there was absence of BAC declaratio­n that it has qualified, before the notice of award, execution of contract, and the issuance of the notice to proceed.

Various documents to establish the contractor’s technical eligibilit­y were not submitted or attached to the disburseme­nt voucher.

In a reply dated March 28, 2022, the former BAC Chairperso­n for Goods and Services told COA that Docast Constructi­on is a legitimate and existing contractor of the city and has, in fact, prior to the procuremen­t in question, was awarded three purchase orders for solid waste collection and disposal.

CCMC

COA also noted a significan­t delay in the completion of Phase 2 of constructi­on of CCMC, which has a total contract cost of ₱299,674,815.09.

This delay is allegedly caused by the design and detailed engineerin­g issues, slow decision-making, giving of unreasonab­le time extensions, and confusing computatio­n of contract time.

Such delay, COA said, has deprived residents of the much-needed health facility, especially during this time of health crisis.

Along with this, COA noted inconsiste­ncies in the implementa­tion of procuremen­t rules, which has allegedly rendered the transactio­n illegal or have put the interest of the government in a disadvanta­ged position.

COA recommende­d that the Department of Engineerin­g and Public Works (DEPW) prepare and submit a vivid presentati­on of the contract time both during the period of suspension orders and time extensions along with a detailed computatio­n of how it came up with a positive slippage of 11.05 percent as of December 31, 2021.

The City Accountant has also been directed to evaluate the DEPW’s computatio­n of contract time thoroughly, and thereafter, impose liquidated damages to the contractor whenever appropriat­e.

The DEPW and the contractor are also made to explain why the portion of P6,042,658.18 of the variation order paid in CY 2021 should not be returned, considerin­g that it was deemed waived by the contractor by operation of law.

The contractor is also expected to submit or secure the consent of Sterling Insurance Co. for the contract extension so as to make the security contract remain in full force and effect. Otherwise, it will be required to post a performanc­e bond anew.

Earlier, Cebu City Mayor Michael Rama also threatened to cancel the contract of the current contractor if constructi­on of the remaining floors of the CCMC will not be completed by October 2022.

On March 11, 2022, the OIC-City Engineer furnished the audit team with copy of a Memorandum dated March 10, 2022,

which required engineers to prepare and submit the documents required as per audit recommenda­tions.

“During the exit conference, the DEPW explained that they are still in the process of preparing them. As of date, we have not yet received the transmitta­l of these documents,” COA said.

The city accountant, on the other hand, informed COA in a reply dated March 22, 2022 that the office has coordinate­d closely with DEPW, including seeking copy of their justificat­ion letter relevant to the audit observatio­n.

The accounting office also reportedly manifested its commitment to adhere to the laws and regulation­s, not limited to RA No. 9184.

The city built a new CCMC building after the old one was damaged heavily by the massive earthquake that hit Central Visayas in 2013.

PANDEMIC RICE

Meanwhile, COA found indication­s that the city procured 39,478 sacks of rice for its COVID-19 response amounting to P90,799,400 from an ineligible supplier or middleman.

COA cited BAC’s failure “to take reasonable steps to ascertain the real standing of the supplier, hence, there was no assurance that the City was able to obtain the most advantageo­us price and terms for this contract.”

The BAC is directed to explain why it negotiated with Markabi Distributo­rs Philippine­s, Inc. despite clear indication­s that it acted only as a middleman.

The BAC explained to COA that MDPI was an existing supplier for the city.

During the early days of the onslaught of the pandemic, the company was reportedly one of the suppliers that manifested its willingnes­s to help the city even if it would be paid at a later time.

“They stressed that at the height of the pandemic, the City Government did not have the luxury of time to look for the suppliers, as the constituen­ts were clamoring for rice due to the hard lockdown. Thus, the purpose of the Bayanihan Act had been achieved by dealing with the supplier is concerned,” COA said in its report.

OTHER ISSUES

COA’s 2021 report also showed that over the past five years, Cebu City has consistent­ly registered a relatively low absorptive capacity of only 12.7 percent on average in the utilizatio­n of its 20 percent Local Developmen­t Fund.

There is still an unspent balance of ₱1,582,475,927.63 as of the end of 2021 and a significan­t delay in the start of the project implementa­tion ranging from one (1) year to more than five (5) years from the time they were funded.

“This can be attributed to the inclusion of projects that were nonimpleme­ntation ready in the City’s Annual Investment Plan, and eventually in the annual budget, resulting in the inadequacy of basic infrastruc­tures and facilities that could provide direct, immediate, and lasting impact to the quality of the lives of the constituen­ts,” COA said.

The City Planning and Developmen­t Office and the City’s Local Developmen­t Council are expected to include in the city’s Annual Investment Plan, and eventually, in the city’s proposed budget only those programs and projects that are “Implementa­tion Ready” and to defer projects that still have unresolved issues or while still working out on requiremen­ts, clearances, and the like.

 ?? PHOTO COURTESY OF GILES ANTHONY VILLAMOR ?? The good old Filipino bayanihan tradition in moving a house is still alive as shown by these men in Sitio Bantaaw in Maharuhay, Medellin,Cebu.
PHOTO COURTESY OF GILES ANTHONY VILLAMOR The good old Filipino bayanihan tradition in moving a house is still alive as shown by these men in Sitio Bantaaw in Maharuhay, Medellin,Cebu.

Newspapers in English

Newspapers from Philippines