The Philippine Star

COA: P214-M project for informal settlers remains idle

- – Elizabeth Marcelo

The Commission on Audit has called out the Social Housing Finance Corp. (SHFC) in connection with a housing project worth P214 million in San Jose del Monte, Bulacan which remains idle despite its completion last year.

In a report recently posted on its website, COA said site inspection last Feb. 2 showed that the zero occupancy was due to non-availabili­ty of water supply.

The COA said the Department of the Interior and Local Government issued a certificat­ion on March 31, 2014 accreditin­g 546 memberborr­owers as beneficiar­ies of the housing project in Barrio Panaklayan Muzon. The project, which is composed of 26 buildings, each a three-story with a loft, was completed and turned over to the ho- meowners’ associatio­n last Nov. 5.

The project is for residents of Phase 10 A and B of Bagong Silang, Caloocan who built their houses along Marilao River.

In its comment to the COA report, the SHFC said it learned of the water connection problem only recently.

However, the COA said the SHFC should have conducted a feasibilit­y study on the provision of basic facilities before it approved the project.

“Non-availabili­ty of water supply deprived the beneficiar­ies to move in to their housing units, resulting in ...non-recovery of... financial exposure in the project... and non-attainment of the objectives of the housing program,” the COA said.