The Department of Transporta­tion (DOTr) started yesterday the gradual deployment of the controvers­ial China-made Dalian trains for the Metro Rail Transit Line 3 (MRT-3).

Transporta­tion Secretary Arthur Tugade, together with officials from the DOTr, MRT-3 and Philippine National Railways, rode the first Dalian train set.

Transporta­tion Undersecre­tary for Railways Timothy John Batan said the first Dalian train set will be initially be used during off-peak hours on weekends for 150 hours.

Batan said the remaining Dalian train sets are still being tested.

One Dalian train set is composed of three light rail vehicles (LRVs).

Incompatib­ility concerns were earlier raised with the 48 LRVs procured by the previous administra­tion for P3.8 billion after they exceeded the weight prescribed in the terms of reference (49,700 kilos vs 46,300 kilos).

Following an independen­t audit by German firm TUV Rheinland, the DOTr said the Dalian trains can still be used if the adjustment­s identified in the audit are addressed “without sacrificin­g the safety, the security, and life of the passengers and the system.”

CRRC Dalian Co. Ltd. of China, the manufactur­er of the trains, agreed to shoulder the cost for technical adjustment­s to be made on the 48 trains as the government aims to integrate the trains into the MRT-3 operations this year.