The Philippine Star

COA flags DOTr over delayed projects

- By ELIZABETH MARCELO – With Iris Gonzales

The Commission on Audit has called out the Department of Transporta­tion (DOTr) over its delayed projects amounting to P8.1 billion, which could have improved the mass transporta­tion system.

In its 2021 annual audit report on the DOTr, the COA noted that as of Dec. 31, 2021, four major projects of the agency have yet to be completed, with delays ranging from four months to five years from the agreed completion dates.

Among the projects cited by the audit body was the supply of 48 light rail vehicles (LRVs) for the Metro Rail Transit Line 3 (MRT-3) capacity expansion projects.

The supply contract, amounting to P3.76 billion, was entered into with Dalian Locomotive and Rolling Stock Co. of China. It was supposed to be implemente­d from Feb. 26, 2014 to Jan. 20, 2017.

The COA, however, noted that as of end-2021, only nine of 48 LRVs were provisiona­lly accepted from Dalian, pending their overhaul and final inspection.

Thirty-nine others have yet to undergo testing and commission­ing, thus were not yet considered as accepted.

The COA in its previous audit report on the DOTr revealed that the LRVs were not equipped with an automatic train protector system when delivered by Dalian, contrary to what was agreed in the contract.

In a comment, the DOTr said it is pursuing a “catch-up implementa­tion” for the project and has requested cash allocation from the Department of Budget and Management in order to settle the outstandin­g payables to Dalian.

The DOTr said that after the payment, conduct of testing and commission­ing works could resume and the accepted LRVs “may then be gradually deployed for passenger service.”

Another delayed project cited in the audit report was the constructi­on of the Unified Grand Central Station – Area A at North EDSA in Quezon City with a contract cost of P2.783 billion.

The project involved the constructi­on of an additional viaduct for Light Rail Transit Line 1 as well as a platform, concourse area and trail track to be labeled as “EDSA Wing Line 1/Line 3” that would connect the LRT-1 and MRT-3.

The COA said the contract, awarded to BF Corp. and Foresight Developmen­t and Surveying Co. (BFC-FDSC), was supposed to be implemente­d for 20 months or 600 calendar days with the original target completion date of Jan. 4, 2021.

However, the BFC-FDSC requested for two contract time extensions (CTEs) – on April 13 and June 18, 2020 – citing the delayed project site access or possession due to restrictio­ns caused by the COVID pandemic.

The approved CTEs prompted the adjustment of the target project completion date to July 31, 2021.

Another delayed project flagged by the audit body was the replacemen­t of license plates of registered vehicle owners supposed to be implemente­d by the DOTr’s attached agency, the Land Transporta­tion Office (LTO).

The COA said that as of the end of 2021, a total of 2.6 million pairs of replacemen­t plates amounting to P1.15 billion, representi­ng the fees collected from the owners of four-wheeled motor vehicles, remained undelivere­d.

The LTO had committed to fast-track the production and issuance of the backlog MV license plates, it said.

The fourth delayed project was the Public Utility Vehicle Modernizat­ion Program (PUVMP), with a total project cost of P392.62 million, supposed to be implemente­d by the Land Transporta­tion Franchisin­g and Regulatory Board.

Newspapers in English

Newspapers from Philippines