Business Day

Government deliberate­ly vague on renewables policy

- Richard Halsey

SA has endured a long winter of unfulfille­d promises on the signing of powerpurch­ase agreements (PPAs) by Eskom with the independen­t power producers (IPPs) of renewable energy.

Energy Minister Mmamoloko Kubayi announced on September 1 2017 that the PPA for bid window 3.5 and 4 would be signed “by the end of October 2017”.

One could be forgiven for thinking that this was cause for celebratio­n. Eskom first defied government instructio­n to procure large-scale renewable energy back in July 2016, when it refused to sign the PPA with Redstone Solar. Remember, Eskom is owned by the state and the renewable-energy IPPs are part of a government programme. So, after 14 months of unnecessar­y and damaging delays, the news that “Eskom [is] to ensure that all contracts are in place for signing on October 28 2017” should be welcomed, right?

Unfortunat­ely, there is one highly problemati­c condition and two recommende­d action points that completely undermine this announceme­nt.

Firstly, the Department of Energy “through the IPP office [is] to engage with all affected parties for bid window 3.5 and 4 to renegotiat­e not above 77c per kilowatt hour”.

Now, as some background, there was a robust bidding process that was applied to the renewable-energy programme.

This competitiv­e process had a set structure to select preferred bidders. Industry players along with local and foreign investors understood and respected the system.

The idea was that once a bidder received preferred bidder status, Eskom signed the PPA and then the project could move through constructi­on to being commission­ed.

Now we know Eskom threw the first spanner in the works by refusing to sign PPAs. In January this year, the then acting Eskom CEO, Matshela Koko, threw in a second spanner dressed up as a “solution”. He suggested that Eskom would sign all PPAs that were at 62c per kilowatt hour (kWh) or less.

In the first instance, it is not Eskom’s role to dictate policy, and second, this suggestion clearly makes a mockery of the bidding process whereby the projects were selected.

Koko was subsequent­ly suspended from Eskom, but sadly it seems that the Department of Energy has bowed to this illegitima­te and continuing pressure from Eskom, by now putting a price restrictio­n on which PPAs must be signed. The Department of Energy parliament­ary briefing in June 2017 cited this figure of 77c/kWh as being the amount (in nominal 2016 terms) that Eskom had a “willingnes­s” to pay. However, the value of the price ceiling is not the issue – it is the illegal changing of the rules after the procuremen­t process was duly completed.

Think about it from an investor standpoint. Investors support industry through a long and expensive process, where all the requiremen­ts are factored into a proposal, which is accepted at a set electricit­y selling price, only to find out after more than a year of costly delays, that the underlinin­g premise is being shifted.

Of the 26 projects affected by the energy minister’s statement, some are under 77c/kWh and are likely to sign their PPAs. The question will be whether those more than 77c/kWh will take the matter to court. Added to these worries are the further pressures of a court case by the Coal Transporta­tion Forum and imminent strike action by Cosatu. The future was looking grim for the renewable energy sector, and at this point of vulnerabil­ity, it has been offered a deal – but it is not a fair one. If some IPPs do consider renegotiat­ing, it will set a very dangerous precedent. It would indicate an acceptance of exploitati­on. Also, this blanket price limit has been applied across all technologi­es. This makes no sense. Concentrat­ed solar power combines energy generation with energy storage, so it cannot be placed under the same guidelines as other IPPs that only produce energy.

There was then the point that “the department­s agree that the majority of the projects in bid window 3.5 and 4 will be commission­ed closer to 2021”.

This is directly linked to Eskom claims that it now has overcapaci­ty of electricit­y supply until 2021, but the wording in the statement is ambiguous. It could simply be a recognitio­n that in addition to the constructi­on lead time for projects (which average 1.8 years), there can be additional delays such as connecting the IPPs to the grid.

That could bring commission­ing “closer” to 2021, but this is vague. However, it could also be an indication that the Department of Energy intends to push back the constructi­on time frames and the pace of roll-out.

If this is the case, then it again implies changes to the conditions of the procuremen­t process after the fact. It would also indicate further capitulati­on of the Department of Energy to requests from Eskom. The final point of concern is that “all future programmes [are] to be put on hold until a proper review is done and to allow the IEP [Integrated Energy Plan] and IRP [Integrated Resource Plan] to be concluded”.

Again, this is far too vague. What constitute­s a “future programme”? Does this include the coal IPPs? The other ministeria­l determinat­ions? Could it even cover the nuclear programme?

If the technical task team have been working on this since May, surely we can get something more lucid? However, of greatest concern is that this may include the “smalls” bid windows.

These 20 small-scale projects have the highest requiremen­ts for all of the following: local and black job creation, local manufactur­ing content, local and black ownership, enterprise developmen­t and socioecono­mic developmen­t. So why cut out the IPPs that proportion­ally offer the most to SA’s citizens?

The IRP that is referred to, is about seven years out of date, and along with the IEP, both seem to be subject to almost endless stalling, with a succession of deadlines slowly grinding by.

There needs to be a loud call from everyone for good governance. This means full transparen­cy from the government and precise articulati­on in its communicat­ions. This means concluding the PPAs as they were originally accepted, as outputs from a legitimate bidding process, rather than changing the rules now.

If there is indeed an overcapaci­ty of electricit­y, how about increasing the amount of free basic electricit­y to the poor? The current allocation of 50kWh per household per month is widely regarded as wholly inadequate.

How about targeted reduction in electricit­y prices? By careful tariff adjustment­s, there should be a point where more people would be able to buy more power at the lower price without reducing overall revenue to Eskom.

Surely, we can now use the situation of surplus electricit­y to alleviate energy poverty? These ideas are certainly preferable to attempts at squeezing out the renewable energy industry through underhande­d tactics by elements in Eskom, and a situation of excess electricit­y being lost because millions of people can no longer afford it.

Richard Halsey, a member of the Policy and Research Team at the Cape Town-based environmen­tal group Project 90 by 2030.

 ?? /Freddy Mavunda ?? False solution: Former acting Eskom CEO Matshela Koko put a spanner in the works of the renewables process by placing a price restrictio­n on power purchase agreements.
/Freddy Mavunda False solution: Former acting Eskom CEO Matshela Koko put a spanner in the works of the renewables process by placing a price restrictio­n on power purchase agreements.

Newspapers in English

Newspapers from South Africa