Business Day

Study suggests ways power costs can be cut

- Carol Paton Deputy Editor patonc@businessli­ve.co.za

Eskom should curtail the constructi­on of Kusile and retire several of its old coal-fired power stations early to save itself billions and shield consumers from excessive energy costs, a new study suggests.

The study, by consultanc­y Meridian Economics, also says that if SA is to pursue a leastcost path for energy generation in the future, it does not need a gas, coal or nuclear procuremen­t programme but should accelerate the installati­on of more renewable energy, the price of which is falling.

The release of the Meridian study at Wednesday’s Windaba conference in Cape Town came as internal Eskom documents on Monday revealed the extent of Eskom’s financial problems, and that by the end of January, the company will be R5bn in the red and unable to pay suppliers or salaries.

Eskom also faces an excess of supply – equal to at least the size of the entire Medupi plant – in the foreseeabl­e future.

Meridian MD Grove Steyn said that Eskom’s tariffs, which are the highest in SA’s history, were a direct consequenc­e of its large, expensive build programme in a context of stagnant electricit­y demand.

The study modelled scenarios for the least-cost operation of SA’s power system and calculated the cost to it of removing each one of the power stations. It also investigat­ed the incrementa­l costs associated with running a particular station for its remaining life.

This makes it possible to estimate the alternativ­e cost of meeting demand if a station is decommissi­oned early, or if new plant constructi­on is cancelled.

“If the system can meet demand over the same period by using alternativ­e resources such as other existing coal stations, wind and solar – but at a lower cost than the cost of electricit­y from a particular coalfired power station – it makes economic sense to decommissi­on that station early, or not to complete it,” Steyn said.

The key findings were that the early decommissi­oning of the Grootvlei, Hendrina and Komati power stations would save R12.6bn in present-day values, and that avoiding the completion of Kusile units 5 and 6 could result in a net financial saving of R15bn to R17bn.

“The level of surplus capacity that Eskom now anticipate­s for the foreseeabl­e future is at least equal to what an entire Medupi or Kusile power station provides, or more.

“The unavoidabl­e conclusion is that Eskom is still spending vast amounts of capital on a power station constructi­on programme that [the country] does not need and Eskom cannot afford,” said Steyn.

Eskom has not commented on the Meridian study, which had also been presented to the National Energy Regulator of SA (Nersa) hearings in Cape Town on the Eskom tariff applicatio­n earlier in November. The utility has previously dismissed suggestion­s that its capital programme should be curtailed to save costs.

The Nersa hearings continue in Johannesbu­rg on Thursday.

 ?? /Sunday Times ?? White elephant: Eskom’s Kusile power station project in Mpumalanga. A study has found that avoiding the completion of Kusile units 5 and 6 could result in a net financial saving of R15bn to R17bn.
/Sunday Times White elephant: Eskom’s Kusile power station project in Mpumalanga. A study has found that avoiding the completion of Kusile units 5 and 6 could result in a net financial saving of R15bn to R17bn.

Newspapers in English

Newspapers from South Africa