Group Five: claim is ‘ sinister’

• Constructi­on firm battles it out in court as Cenpower goes after bonds

- Siseko Njobeni Industrial Writer njobenis@businessli­ve.co.za

Group Five, which is facing a claim of more than six times its market capitalisa­tion, on Wednesday dismissed as baseless Ghanaian company Cenpower Generation’s allegation­s of a breach of contract regarding a delayed power project.

Group Five, which is facing a claim of more than six times its market capitalisa­tion, on Wednesday dismissed as baseless Ghanaian firm Cenpower Generation’s allegation­s of a breach of contract regarding a delayed power project.

In efforts to ward off Cenpower’s $62.7m claim, the struggling constructi­on company on Wednesday told the high court in Johannesbu­rg it is not in breach of the contract for the 340MW gas- and oil-fired combined cycle power plant in Kpone, Ghana.

Group Five legal representa­tive Andre Gautschi disputed Cenpower’s claims that it is in breach of contract. “If you are going to make a demand, there must be a breach,” Gautschi told the court.

Gautschi said Group Five is not at fault for the missed October deadline for the commission­ing of the plant.

He reiterated the company’s assertion that the delay is due to contaminat­ion of the fuel provided by Cenpower.

“The provision of fuel is the client’s responsibi­lity,” Group Five said on Tuesday.

The two companies are at loggerhead­s over Cenpower’s allegation­s regarding Group Five, which is building the $410m Kpone power station, and Cenpower’s recent written demand for $62.7m from Standard Chartered Bank and HSBC, Group Five’s bank-guarantee providers. The claim dwarfs Group Five’s market capitalisa­tion of R129.1m.

Cenpower wants to recoup the money from Group Five’s performanc­e and retention bonds, the value of which are 15% and 10% of the project’s overall costs, respective­ly.

Companies in the constructi­on industry use performanc­e bonds to mitigate the risk of a contractor failing to fulfil contractua­l obligation­s. If a project does not meet the contractua­l standards, the client can make a claim against the bond.

A retention bond protects the client after the project has been completed. It is security for the owner of the project and is used to remedy defects, he said.

Group Five has applied for an interdict against Cenpower’s claim, which the company has described as improper.

Gautschi questioned Cenpower’s claim on the retention bond as that type of bond does not cover constructi­on delays. “The retention bond is there to cover defects,” he said.

Cenpower’s reasons for laying claim to the retention bonds are obscure and sinister, he told the court. “It is a dishonest claim,” he said.

In its results statement for the year to end-June, Group Five said the maximum penalty it faces for missing the original deadline for completing Kpone is capped at $62.5m. It said the contract with Cenpower provides for claims from both sides.

Group Five has instituted its own claims regarding the contract but has declined to reveal the value of them.

The court granted an interim order, interdicti­ng any payments to Cenpower until judgment had been handed down.

Group Five and Cenpower agreed on the interim order. Final arguments are scheduled for Thursday.

“Judgment will be handed down in due course and the group will inform stakeholde­rs once this has occurred,” the company said.

Group Five shares were down 4.35% to R1.10.

 ??  ??