Business Day

Eskom’s Medupi, Kusile hobbled by design flaws

Utility blames Japan’s Mitsubishi Hitachi Power Systems Africa, main contractor for boilers

- Carol Paton Writer at Large

Eskom’s mega power stations Medupi and Kusile, which were intended to alleviate SA’s power constraint­s, have a multitude of serious design and technical flaws that are impeding their operation.

The poor performanc­e of the new power stations is a decisive reason why Eskom is still unable to meet the country’s energy demands despite adding 3,200MW of capacity to the grid since 2015.

The utility went into stage four load-shedding mode on Monday, dropping 4,000MW from the grid, the largest amount to date that it has needed to shed to keep the grid stable. Loadsheddi­ng takes place when demand exceeds supply and customers are dropped from the grid to avoid it from tripping.

Two of the six generating units that failed on Monday, causing the jump to stage four, were at Medupi.

Eskom, which supplies more than 95% of SA’s electricit­y, said the main problems at Medupi and Kusile lay at the door of the main contractor for the boilers, Japanese conglomera­te Mitsubishi Hitachi Power Systems Africa (MHPSA). It is not the first time that Hitachi’s work at Medupi has been found to be defective. In 2013, 10,000 welding faults were discovered when Hitachi failed to heattreat the welds. In 2015, it failed the crucial steam test, which is a necessary step before commission­ing.

In 2015 Hitachi and Mitsubishi Heavy Industries merged their power activities to form Hitachi Power Systems Africa.

Hitachi’s award to build the boilers has always been controvers­ial due to its partnershi­p with the ANC’s investment company Chancellor House.

In 2015 it was fined by the US Securities Exchange Commission for allegedly paying the ANC front a $1m success fee and $5m in “dividends” in connection with the Medupi and Kusile contracts.

A multiplici­ty of faults have been identified, common to both Medupi and Kusile. In its updated tariff applicatio­n to the National Energy Regulator of SA (Nersa), Eskom lists seven tech-

nical and design problems.

These include: the boiler design results in high temperatur­es, which the spray water system cannot adequately cool, leading to frequent tripping; and the design causes excessive ash accumulati­on and ash bags must be frequently replaced, which causes ash blockages, frequent tripping and load losses.

None of the coal mills, which pulverise the coal going into the burner, meet technical specificat­ions, with the consequenc­e that they must be serviced twice as frequently as usual.

The gas air heaters, which capture waste heat and transfer it to combustion air, enhancing the efficiency of the boiler, do not meet technical requiremen­ts. The dust-handling plant, which is vital for reasons of safety, environmen­tal and occupation­al health, needs more frequent maintenanc­e due to high ash accumulati­on, leaks and the low availabili­ty of spare parts.

The distribute­d control system — the computeris­ed control system — frequently fails, causing plant trips and does not meet technical requiremen­ts. Lastly, there is a high number of vibrations on the cooling loop.

Several of these problems are adversely affected by poor coal quality, Eskom’s presentati­on to Nersa states.

The presentati­on also lists a shortage of skilled people and unavailabi­lity of spare parts as an eighth factor negatively affecting Medupi and Kusile.

The result of the problems has meant that Medupi’s unit 6 — which was the first of three so far commission­ed — has barely reached 60% of its capacity since June 2018.

The remaining two units perform at about 70% capacity.

In response to questions last week, Eskom’s COO Jan Oberholzer laid most of the problems at the door of Hitachi Power Systems Africa, but added that these were being managed by applying the terms of the contract between the companies.

Eskom has assembled teams of specialist­s to rectify the major defects and technical workstream­s have been establishe­d with contractor­s.

“Eskom will attempt to resolve issues in terms of the contracts and may institute legal proceeding­s only should contractua­l resolution not be possible ...” he said.

“It is Eskom’s position that the contractor will fix and pay for the faults.”

A spokesman for Hitachi Power Systems Africa, Nicolas Meyer, said the company did not want to comment.

In another blow to the plants, it was reported by EE Publishers on Monday that Clyde Bergemann Africa — a main contractor to Eskom for the ash-handling systems and a subcontrac­tor to Hitachi Power Systems Africa — has filed for business rescue. Employees walked off the site at Medupi and Kusile after they were not paid for the month of January.

 ?? /Masi Losi (See Page 2) ?? Sticks to her story: Former ANC MP Vytjie Mentor arrives at the state capture commission of inquiry. On Monday she insisted that she travelled on a Monday in October 2010 to meet former president Jacob Zuma. The airline, however, has no record of her trip.
/Masi Losi (See Page 2) Sticks to her story: Former ANC MP Vytjie Mentor arrives at the state capture commission of inquiry. On Monday she insisted that she travelled on a Monday in October 2010 to meet former president Jacob Zuma. The airline, however, has no record of her trip.

Newspapers in English

Newspapers from South Africa