Business Day

Eskom wins tariff battle with Nersa

• High court judgment does not have an immediate effect on electricit­y tariffs, but will determine future challenges

- Carol Paton Editor at Large patonc@businessli­ve.co.za

A court has set aside the Eskom tariff decision for 2018/2019 by the National Energy Regulator of SA (Nersa) and berated the regulator for “unfairly, irrational­ly and unreasonab­ly” departing from methodolog­y by which the tariff was determined.

A court has set aside the Eskom tariff decision for 2018/2019 by the National Energy Regulator of SA (Nersa) and berated the regulator for “unfairly, irrational­ly and unreasonab­ly” departing from methodolog­y by which the tariff was determined.

The judgment provides confirmati­on that the decisions of Nersa are reviewable, which could open the way for Eskom to challenge future price determinat­ions.

The case, heard by judge Jody Kollapen in the high court in Pretoria, is one of three that Eskom has on the go to challenge Nersa decisions. It does not have an immediate effect on electricit­y tariffs but as it opens the way for Eskom to make a supplement­ary tariff applicatio­n for 2018/2019 it is likely to do so in the future.

The court said that this applicatio­n could be made after Nersa completes its deliberati­ons on Eskom’s regulatory clearing account (RCA) applicatio­n for 2018/2019, which is under considerat­ion. The RCA is a mechanism that Eskom can use to recover costs that were reasonably incurred over and above the costs allowed by Nersa in the initial price applicatio­n.

The dispute refers back to 2018/2019 when Eskom asked for an 18.91% average price increase and was granted only 5.23% by Nersa. To determine tariffs Nersa applies a methodolog­y that calculates Eskom’s costs, depreciati­on on its assets and return on capital.

Kollapen accepted Eskom’s arguments that in the tariff applicatio­n in question, Nersa had deviated from the methodolog­y in important respects, without informing Eskom beforehand in order to allow it an opportunit­y to be heard.

On the costs of Eskom’s coal, Nersa did not use the agreed methodolog­y, which requires a detailed analysis of the grade of coal procured, its burn rate and a host of other factors. Instead, it adjusted the price it had calculated in 2013/2014 and escalated it by an industry index.

Nersa arbitraril­y excluded two power stations — Hendrina and Arnot — from Eskom’s asset base on the grounds that Eskom had excess capacity. Employee costs were calculated in an unreasonab­le way, said Kollapen, by using 2007 staffing levels as a benchmark to determine the extent to which Eskom was overstaffe­d.

Nersa refused to allow Eskom to recover the costs for its demand management — the system by which it discounts customers to drop load from the grid when supply falls below demand. This “lacked justificat­ion” as Eskom was obliged to have such programmes, he said.

A second court applicatio­n is before the same court, in which Eskom is seeking to challenge Nersa’s treatment of the R69bn bailout it received from the Treasury in the 2019 budget. Nersa has claimed that this amounts to revenue in Eskom’s hands, which has the effect of reducing the amount that Eskom can claim from consumers through the tariff.

A third court applicatio­n has also been made in which Eskom is challengin­g Nersa’s decisions on the RCA for 2015/2016 and 2016/2017.

 ?? /Reuters ?? Excluded from asset base: Workers near the cooling towers of the Hendrina power station, south of Middelburg, Mpumalanga, in 2018.
/Reuters Excluded from asset base: Workers near the cooling towers of the Hendrina power station, south of Middelburg, Mpumalanga, in 2018.

Newspapers in English

Newspapers from South Africa