Business Day

New rule for green projects will protect grid access

- Denene Erasmus

New renewable energy projects that will be built close to existing electricit­y grid infrastruc­ture will need a letter from Eskom approving the project location.

That is according to an amendment to the requiremen­ts for environmen­tal authorisat­ion gazetted on Monday by the department of environmen­tal affairs. It requires that a proponent requests and obtains a consent letter from Eskom confirming that the proposed layout of the facility will not unnecessar­ily obstruct access to the main electricit­y transmissi­on or distributi­on substation.

“The amendment is necessary to ensure that the full potential of the investment into electricit­y infrastruc­ture can be realised,” the department said.

The requiremen­t will apply only to new projects and not to any applicatio­ns for environmen­tal authorisat­ion submitted before the publicatio­n of the amendment.

The department told Business Day the amendment is required to ensure that both main transmissi­on and distributi­on electrical sub-stations “are not obstructed by the encroachme­nt of developmen­ts which limits the ability to serve several clients from the same substation”.

It specifies that developers must submit the letter as part their applicatio­n for environmen­tal authorisat­ion for a proposed project if it is located in a radius of 2km of a main electricit­y transmissi­on substation or within 1km of a main electricit­y distributi­on substation.

If Eskom does not reply to a request for a letter of consent within 45 days, and if the applicant can prove it has followed up the matter with Eskom, the department will assume Eskom has no objection to the location.

A lack of available grid access is one of the main barriers to the rollout of new renewable energy projects in SA.

Eskom’s latest generation connection capacity assessment shows there is no grid capacity available in any of the three Cape provinces. These areas remain in high demand due to their abundant energy resources for renewable generation. About 20,000MW of capacity is available in the rest of the country.

Eskom says in the assessment that unlocking capacity in the Cape provinces will require a significan­t amount of transmissi­on network investment, which often takes several years to develop and construct.

“The required transmissi­on corridor strengthen­ing to unlock grid capacity and alleviate these constraint­s will only be commission­ed from 2027 onwards,” Eskom states in the document.

Eskom has conducted curtailmen­t studies to provide generation developers with an alternativ­e if they still want to connect in these constraine­d areas, but that would involve the mandatory reduction of output from a renewable plant.

The framework must still receive approval from the regulator. “Generation developers are, therefore, strongly encouraged to consider developing their projects in those areas with remaining capacity,” Eskom says in the assessment.

Newspapers in English

Newspapers from South Africa