Cape Argus

Court’s curb on nuke plan hailed

Environmen­tal groups, activists sing in the rain after ruling

-

OPPOSITION parties and activists have hailed as a victory the Western Cape High Court ruling that has effectivel­y called a halt to the government’s controvers­ial nuclear power expansion programme.

Judge Lee Bozalek, in response to an applicatio­n from environmen­tal groups, set aside two determinat­ions by former energy minister Tina Joemat-Pettersson, reached respective­ly in 2013 and 2016, that paved the way for Eskom’s current process of procuring an additional 9 600 megawatts of nuclear power.

Judge Bozalek faulted the National Energy Regulator of South Africa for failing to act in the public interest by approving the 2016 determinat­ion within days, without soliciting any public input.

The DA’s energy spokespers­on, Gordon Mackay, said the ruling was a reprieve for a country that would have been saddled with a nuclear programme it cannot afford.

“The court’s findings have greatly narrowed government’s ability to legitimate­ly procure additional nuclear capacity,” he said.

“The DA will now work to ensure that Eskom halts all work on the nuclear procuremen­t process and will seek to guarantee that no Request for Proposal (RFP) is issued. Any attempts by Eskom to subvert the decision of the court will be challenged by the DA.”

Judge Bozalek also found that the utility’s request for informatio­n on potential bidders in December was unlawful, as was the country’s nuclear co-operation agreement with Russian state nuclear group Rosatom – which was seen as the frontrunne­r to secure a contract to build new nuclear power plants. The ruling also set aside similar agreements with the US and Korea.

The EFF welcomed the court ruling, saying the accord would have contribute­d to the leeching of state resources by private individual­s. “The declaratio­n of the agreement to be unconstitu­tional is a victory against kleptocrac­y and state capture by the Gupta family.”

Mackay said that in simple terms, the court ruling meant that since none of the government’s decisions to procure more nuclear power plants were legal, the procuremen­t process must stop.

“The court has ruled that all Requests for Informatio­n (RFI) and potential RFPs pursuant to the outdated Integrated Resource Plan (IRP) and Section 34 Ministeria­l Determinat­ions are set aside. This means Eskom must cease all work being done on nuclear procuremen­t with immediate effect.”

Eskom had been expected to issue a formal Request for Proposals by the end of June.

The case was brought by Earthlife Africa Johannesbu­rg (ELA-JHB) and the Southern African Faith Communitie­s’ Environmen­t Institute (SAFCEI) against the government in 2015. Earthlife activists were jubilant after hearing the ruling and danced in the rain outside the high court.

Adrian Pole, a lawyer for the two applicants, said the judgment meant there was no decision in terms of the relevant empowering statute that new nuclear generation capacity is needed.

“Before any nuclear procuremen­t can proceed, the minster of energy (in concurrenc­e with Nersa) will be required to make a new determinat­ion in accordance with a lawful process that is transparen­t and includes public participat­ion.

“This will necessaril­y require disclosure of relevant informatio­n that to date has been kept from the public, including critical informatio­n on costs and affordabil­ity.” – ANA

 ??  ??

Newspapers in English

Newspapers from South Africa