Engineering News and Mining Weekly

Diamond miner progresses Botswana shaft sinking

-

Diamond explorer and miner Lucara Diamond Corporatio­n made significan­t shaft sinking progress in 2023 at its Karowe Undergroun­d Project (UGP), in Botswana, where the miner invested $101.3-million for the year, focusing on developmen­t of the undergroun­d portion of the project.

Developmen­t efforts in the fourth quarter of 2023 comprised mainly shaft sinking, lateral developmen­t and grouting programmes in both the ventilatio­n and production shafts of the Karowe UGP.

As a result, at the end of 2023, the production and ventilatio­n shafts were both at 348 m below collar, or 666 m above sea level, and the process of establishi­ng the first shaft stations and lateral connection between the two shafts on 670 level, had started.

The miner is expanding the Karowe mine, the existing openpit of which is expected to be depleted in 2026, with plans underway to develop the undergroun­d orebody, thereby extending the life-of-mine to at least 2040.

The Karowe UGP is designed to access the highest value portion of the Karowe orebody, with initial undergroun­d carat production predominan­tly from the highest value eastern kimberlite unit.

During the fourth quarter of 2023, the ventilatio­n shaft was sunk to 76 m, the 718 slinging cubby was completed and the 670-level station catwalk was establishe­d, while the lateral station developmen­t was started.

Total lateral developmen­t of the ventilatio­n shaft in this period was 97 m, and developmen­t equipment – including a Kubota machine, a Sandvik DD321 boom jumbo drill and a Caterpilla­r R1300G 7 t load-haul-dump unit – was mobilised at the 670-level for lateral developmen­t mining.

During the period, a total of 30 m of lateral developmen­t for the production shaft was completed, with activities in this shaft including the shaft sinking of 114 m and the establishm­ent of the 670-level station catwalk.

Additional­ly, Lucara also completed the commission­ing of the temporary bulk air coolers at each shaft, while constructi­on at the permanent bulk air coolers at the production shaft continued.

Both shafts have completed sinking through the water-bearing Ntane and Mosolotane sandstones. Sinking and lateral developmen­t during the fourth quarter took place in the Thalbala mudstone in dry conditions.

The mid-2023 appointed president and CEO William Lamb noted that this UGP progress was part of Lucara’s effort to focus on the UGP and, with the attendant resource deployment, presented an “exciting and valuable future for Lucara”.

Meanwhile, Lucara also signed a contract for fabricatio­n of the permanent personnel and materials winder during the fourth quarter of 2023, representi­ng the last major component for the permanent winders of the production shaft.

Mining engineerin­g advanced with a focus on supporting shaft sinking, undergroun­d infrastruc­ture engineerin­g and finalising level plans, Lucara reports.

UGP Scheduling

Lucara updated the Karowe UGP schedule and budget during July 2023 in response to slower-than-planned ramp-up to expected sinking rates in 2022, and, to account for time incurred to complete grouting programmes while mining through the water-bearing geological zones.

The ventilatio­n shaft is currently 61 m, or about 26 days, ahead of the July 2023 schedule update; while the production shaft is 11 m, or about 24 days, behind the July 2023 schedule update, mainly owing to an unschedule­d grouting event.

These chemical grouting programmes took longer than anticipate­d as a result of a combinatio­n of high-water volumes in the sandstone lithologie­s between the depths of 144 m to 262 m below the shaft collar, as well as owing to technical challenges associated with the transition to main sinking.

The updated schedule incorporat­es a 28% increase in the duration of constructi­on, extending the anticipate­d start of production from the undergroun­d from the second half of 2026 to the first half of 2028.

The revised forecast of costs at completion is $683-million (including contingenc­y) – a 25% increase to the May 2022 estimated capital cost of $547-million.

The forecasted increase of $136-million in estimated capital to reach project completion is predominan­tly related to increased schedule duration and related labour costs, which make up about 56% of the total increase; grouting costs, which account for about 20% of the total increase; while the balance is attributab­le to owner's costs, procuremen­t and indirect project costs.

 ?? ?? KAROWE UNDERGROUN­D DEVELOPMEN­T Lucara Diamond Corporatio­n is expanding the Karowe mine to access the undergroun­d orebody, thereby extending the life-of-mine to at least 2040
KAROWE UNDERGROUN­D DEVELOPMEN­T Lucara Diamond Corporatio­n is expanding the Karowe mine to access the undergroun­d orebody, thereby extending the life-of-mine to at least 2040

Newspapers in English

Newspapers from South Africa