George Herald

Good progress on Gray St upgrade

- Blake Linder

The redevelopm­ent of Gray Street, a major artery at the heart of the Knysna CBD, is roughly one-third complete, according to the municipali­ty, with the first section expected to open in the coming weeks.

Previously, now-suspended municipal manager Dr Sitembele Vatala said the R17-million reconstruc­tion project would include the replacemen­t of the old water pipeline, the total rebuilding of the road, parking, as well as the beautifica­tion of the area. Work on Block A of Gray Street (between Waterfront Drive and Gordon Street) began in late February / early March this year.

However, only four weeks into the project it was hit by a major setback - lockdown. This has had a negative impact on the timeline of completion, according to municipal spokespers­on Christophe­r Bezuidenho­udt. "Covid-19 regulation­s shut the site down and delayed the project by two months. The new expected completion date is September 2021." Despite this significan­t setback, project manager Irvin Erasmus has stated that everything is running smoothly outside the framework of the lockdown.

"So far so good, we're about 90% complete with Block A, and it should be opened in the next 14 days or so," Erasmus said. "Lockdown saw us close site for 47 days so it is frustratin­g, but we haven't had any other issues and have begun work on Block B already."

Block B is the next section of Gray

Street to be upgraded, stretching between Gordon and Trotter streets.

According to Bezuidenho­udt, the upgrading of sidewalks is included in the project, and unfortunat­ely this could lead to the removal of some trees in Gray Street. "All trees that impede pedestrian movement or parking will be removed as identified in the streetscap­e design," he explained. The remainder of the street is being tackled on a block-by-block basis.

 ?? Photo: Blake Linder ??
Photo: Blake Linder
 ??  ??

Newspapers in Afrikaans

Newspapers from South Africa