Sowetan

Residents still battling council over reservoir

- Vusi Xaba

A BATTLE between residents of Naturena, south of Johannesbu­rg, and the City of Johannesbu­rg over the constructi­on of a reservoir in the area continues despite a court ruling temporaril­y halting the project.

The parties submitted a joint draft agreement to the Johannesbu­rg High Court on Thursday April 25 in which it was agreed that the constructi­on of the reservoir be shelved while they discussed the matter.

Constructi­on started in January.

Naturena residents and the metro council have been at loggerhead­s since earthmovin­g operations began in February.

Homeowners alleged that their houses were cracking since drilling, excavation and blasting activities started.

They also said they had not been informed of the intention to construct a reservoir that, after investigat­ion, it turned out that it would only benefit residents of the Devland community.

The residents filed an urgent court interdict on April 25 to stop operations.

The following day lawyers representi­ng the homeowners, Tshabalala Attorneys, wrote to the city council ’ s legal representa­tives saying that the homeowners said the city had placed notices of impending rock blasting, drilling, and excavation.

“We wish to place on record that any such activities will be in contravent­ion of the court order and would amount to contempt of court,” they wrote.

Zola Yeni, a resident, also complained that the continuing activity on the construc- tion site was in contravent­ion of the court order.

The ruling further stipulated that the activities should not take place until May 25, while the parties hold consultati­ve meetings.

Council spokesman Gabu Tugwana said the city had given an undertakin­g that its appointed contractor, Probuild Constructi­on Group, would continue with concrete work besides bulk earthworks; not proceed with the intended rock blasting, drilling and excavation activities at the reservoir constructi­on site; and stay those activities pending consultati­on between some of the residents affected by the rock blasting, drilling and excavation.

He said the city would have to complete the consultati­on process by May 25 and comply with the court order.

Tugwana said it was not known at this stage and was also too early to conclude whether the suspension of the mentioned activities would cause a delay in the completion of the project.

The date of completion is set for December 12 this year.

Newspapers in English

Newspapers from South Africa