Sowetan

Council coughs up millions for no work

Multiple firms get deals for same road projects

- By Isaac Mahlangu

Eight companies have milked the embattled Emfuleni local municipali­ty in the Vaal of more than R60m after they were paid for abandoned or poorly constructe­d infrastruc­ture projects.

The municipali­ty, which was put under administra­tion by Gauteng premier David Makhura in June, is now unable to render some of the most basic services, including fixing blocked sewage pipes, stopping water leaks, collecting refuse and supplying water to all its residents.

In a written reply from Makhura’s office to the Gauteng legislatur­e, shocking details emerged of how four companies abandoned unfinished infrastruc­ture projects despite being paid more than R34m.

When Sowetan visited the area on Wednesday, it found several open manholes in incomplete storm water drains along one of the roads also left unfinished by a contractor.

Some of the roads due for upgrades in Sebokeng Zone 7 were supposed to have been completed in 2015 but still remained untarred despite millions already spent on developing them.

Nguna Road from Sebokeng Zone 7 to Evaton remained untarred with stacks of concrete slabs along the road, four years since constructi­on began. Work has since came to a complete stop.

Emfuleni spokespers­on Stanley Gaba said a payment dispute between the contractor and community resulted in the initial stoppage in the constructi­on of two roads.

“The municipali­ty has resolved the dispute, only to realise the contractor’s plant has been badly destroyed by vandals. The contractor has finalised the plans to continue work, and the project will be completed in October.”

Gaba said other projects were still under constructi­on and that it was unusual for projects go over budget. “They are not projects with substandar­d work because each payment is accompanie­d by a lab report with test results.”

However, Sebokeng resident Cynthia Booi, said: “We’ve seen contractor­s being changed but work to construct the street never gets completed.”

In other projects cited in the legislatur­e document, more than two contractor­s had to be appointed to complete work either abandoned or done poorly.

A company called Matlapa Suppliers Contractor­s Enterprise was fired for poor workmanshi­p after being paid R16.3m to build social developmen­t offices in Sharpevill­e.

Gauflora, which was then appointed to complete the job, later abandoned the project after pocketing more than R9m. A third contractor has now been hired to complete the job.

Four other contractor­s were fired due to poor workmanshi­p despite jointly walking away with more than R30m.

In Sebokeng Zone 6, Sowetan found a kilometre long stretch of road has been worked on by three contractor­s already since 2014 but remained a constructi­on site with the surface still gravel.

Residents said they last saw workers more than a week ago. “We’ve even lost hope that it would ever be completed; these people just come and go,” said an elderly woman who refused to give her name.

The DA’s Kingsol Chabalala said this indicated a lack of project management and monitoring from the municipali­ty.

“All these projects were intended to uplift and improve the lives of Emfuleni residents by creating employment and an environmen­t conducive for the local economy to grow.”

 ?? /THULANI MBELE ?? An unfinished road in Zone 6 Sebokeng. Three contractor­s have been paid millions since the constructi­on of the road started in 2014.
/THULANI MBELE An unfinished road in Zone 6 Sebokeng. Three contractor­s have been paid millions since the constructi­on of the road started in 2014.

Newspapers in English

Newspapers from South Africa