The Citizen (KZN)

CEO says he’s sleeping well

ALLEGATION: ESKOM OVERPAID BY R1 BILLION

- Roy Cokayne

Basil Read’s Mapasa says power utility mismanaged Medupi and Kusile.

Basil Read CEO Khathutshe­lo “K2” Mapasa admits he is not losing any sleep over the alleged overpaymen­t by Eskom of an estimated R1 billion to a Stefanutti Stocks Basil Read (SSBR) joint venture and another joint venture Stefanutti Stocks has with a different partner.

The overpaymen­t forms part of the almost R4 billion alleged overpaymen­t by Eskom to various contractor­s at Kusile Power Station.

An Eskom briefing document dated June 10, which was compiled in response to a query raised by the chair of the Parliament­ary Standing Committee on Appropriat­ions, said investigat­ions by the Special Investigat­ions Unit (SIU), Bowman Gilfillan and Eskom into these overpaymen­ts to contractor­s at Kusile is ongoing.

Mapasa said Basil Read sold its 50% stake in the SSBR joint venture effective from 1 September 2017, had to obtain Eskom’s consent for this transactio­n, and was given indemnity in a full and final settlement agreement “for whatever claims that can come up historical­ly or in the future”.

Mapasa further claimed that Eskom and Minister of Public Enterprise­s Pravin Gordhan are “playing a bit of politics and semantics” about this matter and denied there was anything irregular about the additional payments made to the SSBR joint venture related to the ‘Package 16’ (miscellane­ous buildings) contract.

“It sounds nice to say you have overpaid a contractor by R1 billion or whatever the number is, but the fact of the matter and reality is that Eskom mismanaged both Medupi and Kusile and this is why there are contractua­l claims,” said Mapasa.

“These [Package 16] buildings were supposed to be built in a certain sequence but when we started doing the building, certain sites were not available, hence the projects were delayed and resulted in extended time. This is not the same as the Guptas actually stealing money.”

Package 16 comprised 81 buildings at Kusile, including the unit auxiliary bays.

The briefing document, commenting on the circumstan­ces that led to the overpaymen­t, said the joint venture put in claims for additional ‘preliminar­ies and general’ (P&G) due to prolongati­on and stacking and working in multiple areas at the same time.

Claims not substantia­ted

The document said these claims were not substantia­ted as required by the contract and that Eskom’s representa­tive and contracts manager made interim payments to the contractor between 2015 to 2018, without the requisite substantia­tion.

It said this was done on the basis that they would conclude an overall “settlement agreement” but stressed there was no consistenc­y or verificati­on of the actual P&Gs being paid on a monthly basis.

The monthly payments, according to the document, varied between R15 million and R50 million a month but no settlement agreement was reached.

It said the new project director in early 2018, stopped the interim payments that were being made and referred the non-payment to the dispute adjudicati­on board (DAB).

“Eskom successful­ly defended this adjudicati­on and is now in mutually agreed discussion­s with SSBR and the standing DAB about the process to determine the actual claim entitlemen­t.

Stefanutti Stocks stated emphatical­ly the company disputes that it or the joint ventures in which it participat­es have been overpaid by Eskom.

 ?? Picture: Moneyweb ?? ABOVE BOARD. Basil Read CEO denies there was anything irregular about the additional payments made to the joint venture related to the ‘Package 16’ contract.
Picture: Moneyweb ABOVE BOARD. Basil Read CEO denies there was anything irregular about the additional payments made to the joint venture related to the ‘Package 16’ contract.

Newspapers in English

Newspapers from South Africa