The Mercury

Contractor­s named in Kusile Power Station constructi­on overpaymen­t

- KAILENE PILLAY kailene.pillay@inl.co.za

◆ ABB SOUTH AFRICA:

The estimated overpaymen­t to ABB SA is around R1 billion. ABB SA was appointed using a closed procuremen­t tender strategy to conduct work on the Hitachi Boiler and Alstom Turbine combinatio­n. The other bidders included Siemens and Maul Bilfinger.

All three companies sent were visited by Eskom Engineerin­g and a mini factory acceptance test (FAT) was done and witnessed on the product.

During this phase, Maul Bilfinger did not meet the FAT and withdrew.

During the tender between Siemens and ABB, the ABB price was higher than the price submitted by Siemens, “however, due to technical price adjustment­s made to the Siemens tender, ABB emerged as the cheaper option”.

Once the execution of the works began, ABB was issued with four major orders to be conducted at Kusile Power Station, which included accelerati­on at the cost of R251 million, a demobilisa­tion claim for R179m, accelerati­on for R290m and cabling for R311m. The report found that these orders did not have all the required particular­s to assess or verify the delays and costs claimed and were grossly inflated.

The Special Investigat­ing Unit (SIU) first met representa­tives of ABB and its legal team in August 2018, at which time the SIU was informed that ABB was conducting an internal investigat­ion following informatio­n that came to its attention through the media.

The SIU and ABB teams met again in January 2019 to discuss the findings at the time. While the SIU is in the process of finalising its own investigat­ion, ABB have verbally offered to pay back approximat­ely R240m.

Numerous employees, including the then project director, employer’s representa­tive and contracts managers, are being investigat­ed by the SIU and none of the main role-players are currently working for Eskom.

◆ TENOVA MINING AND MINERALS SA (PTY) LTD:

The estimated overpaymen­t to Tenova is R735m. Tenova Mining and Minerals was contracted by Eskom for the complete design, procuremen­t, delivery to site, erection, cold and hot commission­ing of the terrace materials handling systems for the Kusile Power Station project in 2015.

Tenova had not been able to complete its tasks due to “delayed access to site and disruption­s” and Eskom agreed to pay it R700m in 2016 for work it had done.

In August 2019, the SIU informed Eskom that it was investigat­ing the Tenova contract for potential overpaymen­t and confirmed two months later that evidence had been referred to the National Prosecutin­g Authority (NPA).

Tenova management said that they were not aware and indicated that they would start an independen­t investigat­ion on the matter. Their feedback is due this month.

The officials involved include the project director, the projects employer representa­tive and the project senior contracts manager at the time who were involved with the settlement and negotiatio­ns.

Two of the contract managers involved resigned in the face of disciplina­ry action by Eskom, based on the SIU’s findings. The other two Eskom officials involved resigned prior to the investigat­ion. The SIU has since referred evidence supporting the institutio­n of criminal charges against seven relevant role-players to the NPA.

The report stated that the SIU was considerin­g institutin­g civil action against the role-players to recover the losses incurred by Eskom.

◆ TUBULAR CONSTRUCTI­ON PROJECTS (PTY) LTD AND GENERAL ELECTRIC:

The estimated overpaymen­t to Tubular Constructi­on is around R450m and R163m, while General Electric (previously Alstom) is estimated to have been overpaid by around R400m.

Tubular had been contracted to work on Kusile’s air-cooled condenser.

The report stated that it remained “questionab­le” whether Tubular Constructi­on provided Eskom with any value and if the contractor was really entitled to the additional payments.

Tubular Constructi­on was also awarded a contract for the waste water treatment plant in December 2012 after a de-scoping exercise from the contract originally awarded to Mott MacDonald PDNA. According to the report, this contract and the circumstan­ces around the de-scoping are also being investigat­ed.

The officials involved include the project director and project employer’s representa­tive who were involved with the negotiatio­ns and approval of the modificati­on at that time.

The Eskom staff involved with this investigat­ion have resigned. However, the SIU referred evidence to support charges against the relevant role-players to the NPA.

This resulted in the arrest of former Eskom group executive for Group Capital Division, Abram Masango; former Eskom senior manager: Group Capital Division France Hlakudi; chief executive of Tubular Constructi­on Tony Trindade and Hudson Kgomoeswan­a in December. They were charged with fraud, corruption and money laundering and granted bail of R300 000 each.

◆ STEFANUTTI STOCKS BASIL READ JV (SSBR) AND STEFANUTTI STOCKS IZAZI JV (SSIJV):

The estimated overpaymen­t is R1bn. SSBR was contracted for the constructi­on of 81 buildings, including the unit auxiliary bays at Kusile power station project. The report stated that SSBR put in claims for additional preliminar­ies and general due to working in multiple areas at the same time.

These claims were not substantia­ted as required by the contract.

Between 2015 and 2018, Eskom made interim payments to the contractor without the requisite substantia­tion as this was done on the basis that they would conclude an overall “settlement agreement”.

The report found that there was no consistenc­y or verificati­on of the claims being paid on a monthly basis.

The monthly payments varied from R15m to R50m a month. The report said Eskom was currently in “mutually agreed” discussion­s with the contractor about the process to determine the actual claim entitlemen­t. SSIJV was contracted for the constructi­on of roads, paving and landscapin­g at the power station.

Regarding SSIJV, the report said during the execution of the contract, certain compensati­on events were agreed and paid without the final measuremen­ts being done.

The contractor has also submitted various other deemed accepted compensati­on events claiming that the work was done and these disputes were in adjudicati­on.

The Eskom staff involved with this investigat­ion have since resigned from the power utility. The contracts are currently under investigat­ion by the SIU, which has to date referred evidence in support of criminal charges against 11 role-players.

“Progress on the investigat­ions may conclude that additional Eskom staff were involved. Action will be taken as soon as the investigat­ion results become available,” the report stated. It added that the SIU was considerin­g institutin­g civil proceeding­s and has requested the appointmen­t of experts to assist in the quantifica­tion of losses incurred by Eskom.

This informatio­n is from a briefing document on the Kusile Power Station contract investigat­ions dated June 10, 2020. It was compiled by Eskom and was a response to a query raised by the Standing Committee on Appropriat­ions in February this year.

This report was attached to a letter by Pravin Gordhan to ANC Chief Whip Pemmy Majodina dated July 6.

Newspapers in English

Newspapers from South Africa