Load-shedding may continue into week

- |

STATE-OWNED power utility Eskom implemente­d stage two load shedding yesterday afternoon.

“Eskom regrets… after having not implemente­d load shedding from December 9, 2018, that Eskom will implement stage two rotational load shedding from (1pm) and is likely to continue until (10pm),” Eskom said.

This was as a result of a shortage of capacity. There was also a need to replenish and preserve emergency water and diesel resources to limit the possibilit­y of load shedding or the magnitude thereof in the following week. Customers were reminded to treat all electrical points as live.

Stage two called for 2 000MW to be rotational­ly load shed nationally. It was conducted as a measure of last resort to protect the power system from a total collapse or blackout.

“We appeal to residents and businesses to use electricit­y sparingly during this period. Please switch off geysers and non-essential lighting and electricit­y appliances.”

Schedules are available on the Eskom website (http://loadsheddi­ng. eskom.co.za).Eskom. Customers could also contact 0860 037 566.