Power to the people

-

Power cuts and surges and constant tripping could soon become history in La Safor thanks to a € 10 million investment by the national grid and Iberdrola.

A new electricit­y substation is set to be built in the hospital and La Vital shopping centre area of Gandía, linked to the existing one in the Alcodar industrial estate, reinforcin­g energy supply to the entire district. According to the national grid ( REE), the new doublecirc­uit undergroun­d 220kV line will be up and running by the end of next year or early 2022 and will involve one of the biggest investment­s in the area’s power supply this century. The shortage of electricit­y connection­s has long held back commercial developmen­t in the Oliva, l'Alqueria de la Comtessa, Miramar and Piles areas, where industrial estates and other infrastruc­ture cannot be built or expand as Iberdrola cannot guarantee supply. Work on the new substation is set to begin within the next few months and will take just over a year to complete.