MATARA-BELIATTA RAILWAY STRETCH TO BE COMPLETED IN SEPTEMBER

- BY S. GALAPATTHI

Engineers are hopeful that the 27 km stretch of railway from Matara to Beliatta in the proposed Matara – Kataragama railway would be completed by September this year.

Project Engineer A.g.c.wimalasuri­ya said a consignmen­t of rails for the project had arrived in the Magampura Port in Hambantota and plate-laying would commence in early May. He said the Matara – Hakmana main road would be temporaril­y closed at the Gabada street, compelling people to use alternativ­e routes.

Engr. Wimalasuri­ya said 85 percent of stage 1 of the project that included 16 undergroun­d crossroads, 8 overhead crossroads, two main bridges, 12 ordinary bridges and two tunnels were now complete. He said the railway stations at Kekenadura, Bambarenda, Weurukanna­la and Beliatta were now being built.

He said constructi­on work of the project costing US$278 million had been undertaken by the China Machinery Import and Export Company. Engr. Wimalasuri­ya said the public would have the opportunit­y to travel by train from Colombo to Beliatta by the end of this year.

 ??  ??

Newspapers in English

Newspapers from Sri Lanka