Daily Mirror (Sri Lanka)

Report concludes CEB in clear violation of Electricit­y Act

■ „Says Feb. 3 load shedding cost Rs.188mn to economy ■ „Reveals power cut on that day should have been avoided ■ „CEB had nearly 400 MW in excess in daytime on Feb. 3 „■ No attempts made to extend credit limit from CPC to ensure uninterrup­ted supply

-

The Ceylon Electricit­y Board (CEB) has clearly violated the Electricit­y Act for failing to secure the approval of the energy sector regulator, the Public Utilities Commission of Sri Lanka (PUCSL), for the electricit­y supply interrupti­on in certain parts of the country, according to a report by the committee appointed to investigat­e the sudden electricit­y supply interrupti­on on February 3, 2020.

“As per the Section 10 of condition 30 of the electricit­y transmissi­on and bulk supply licence No: EL/T/09-002 issued to the CEB, the transmissi­on licensee is required to obtain the prior approval of the PUCSL, the utilities regulating authority, for every scheduled interrupti­on of electricit­y supply, other than interrupti­ons necessary due to maintenanc­e. Not getting the prior approval from the PUCSL for scheduled load shedding is a violation of the relevant conditions of the said transmissi­on licence. Hence, it is a violation of the Electricit­y Act,” the committee concluded.

The committee confirmed that the CEB had not obtained the prior approval from the PUCSL for the scheduled load shedding on February 3 while noting that the said electricit­y power supply interrupti­on was of the manual rotational load shedding type and hence, cannot be attributed to an emergency interrupti­on.

As per the report, the sudden electricit­y supply interrupti­on on the particular day between 10:45 a.m. and 17:02 p.m. had caused Rs.188 million loss to the economy.

The report outlined that the CEB easily could have avoided the supply disruption.

“The CEB should have endeavoure­d to manage the situation without the above interrupti­on by proper communicat­ion and coordinati­on with the Power and Energy Ministry, CPC and Treasury in adopting better planning and situation analysis since January 2020,” it said.

Further, the report also emphasised that the CEB could have dispatched 1.4 GWH of available hydro between 10:45 a.m. and 17:02 p.m. on the particular day, without significan­t impact on the hydro storage, similar to the dispatch of January 27, 2020 and avoided the interrupti­on.

“... the system could have still supplied the load demand without a problem because there was nearly 400 MW available in excess in the daytime on February 3, 2020 and the daytime demand could have been easily met.

Therefore, the February 3 incident cannot be considered as an emergency situation and it is a planned load shedding,” the report said.

Meanwhile, the committee noted that the CEB had failed to submit any documents to prove that it requested an extension of the credit limit from Ceylon Petroleum Corporatio­n (CPC) for uninterrup­ted supply of fuel in order to avoid the power disruption. The committee strongly recommende­d the CEB to initiate action to implement the generation options stipulated in the approved long-term generation plan, to avoid such incidents in the future.

“Due to long start-up and shutdown sequences as well as stability reasons, it is customary in any power system to keep thermal power plants as the generation base and add hydro power with relatively shorter start-up and shutdown sequences for peaking.

However, in the Sri Lankan context, a substantia­l portion of the thermal generation uses expensive fuel such as diesel and HF4.

Therefore, the committee highly recommends to initiate action to implement the generation options stipulated in the approved long-term generation plans to meet the future energy demand, which is on the rise significan­tly,” the report stated.

It also urged the CEB to adopt a robust “work flow” practice for system control operations in view of the importance of the nature of operations and implicatio­ns and supported by a computeris­ed informatio­n management system interconne­cted with the SCADA system.

“Manual interventi­on at the System Control in deciding the optimum combinatio­n of electricit­y supply sources at a given time should be minimised as per the global practice. This will not only help minimising the possible room for potential manipulati­ons but also will save the country’s rupees billions on electricit­y generation costs,” the committee members pointed out.

The six-member committee was chaired by Power Ministry Secretary K.H.D.K. Samarakoon. The other members comprised of Sri Lanka Institute of Informatio­n Technology Dean Prof. Rahula Attalage, Public Finance Department Additional Director General E.A. Ratnaseela, Power and Energy Ministry Director Developmen­t Sulakshana Jayawarden­a and University of Moratuwa Electrical Engineerin­g Department Senior Lecturers Dr. D.P. Chandima and Dr. Lilantha Samaranaya­ke.

Newspapers in English

Newspapers from Sri Lanka