- By Carmel L. Corea

In view of Sri Lanka’s limited land mass and distributi­on of its dense population in the hill country, is it reasonable to use explosives and mine such a large volume of granite? Can Sri Lanka afford to risk landslides and endanger the lives of its people by dump this volume of its granite in the sea to construct a Port City?

The original proposal to create a Colombo Port City was made in 2004. It involved small-scale sea reclamatio­n subjected to a thorough and comprehens­ive study. In 2010, it appears a few senior profession­als in their individual capacities had done an Initial Technical Pre-Feasibilit­y Study, focusing on a small-scale developmen­t of 200 acres (80 hectares), as had been initially planned. Their report was not comprehens­ive and considered as a ‘concept note’.

In October 2012, the Chinese Developer had submitted a project proposal to the Board of Investment. It focused purely on the developer’s interests, his return on investment, marketing perspectiv­e, funding arrangemen­ts, etc. The report does not address the project feasibilit­y at all. However, the project was moved to constructi­on phase without knowing its technical, financial or socio-economic viability.

When work started, there was no infrastruc­ture developmen­t plan in place. It is understood that a draft master plan was submitted to the Urban Developmen­t Authority (UDA) in late January 2015. It was returned to the developer for further improvemen­t, reports Eng. Channa Fernando ( The Sunday Times, 05-042015).

The purpose of the Port City

The Colombo Port City is to be an alternativ­e to the highly congested and unplanned City of Colombo. It is advertised as an iconic business district having shopping and water sports areas, a mini golf course, hotels, apartments, recreation areas and a luxury yacht marina.

Environmen­tal Impact Assessment (EIA)

The EIA process is laid down under the National Environmen­t Act No 56 7 1988 amended in 2000 as Act No 53. It is further prescribed in the Gazette No 772/22 of June 24, 1993. The process includes steps the project proponent should take in submitting preliminar­y informatio­n to the Central Environmen­tal Authority (CEA).

The CEA would decide whether the project could be carried out with an initial Environmen­tal Examinatio­n (EE) or whether there is a need for further consultati­ons requiring the project proponent to respond, before approval is granted. However, it is not clear whether this requiremen­t has been satisfied with regard to the Port City project.

On behalf of the developer, the Sri Lanka Ports Authority (SLPA) made an initial applicatio­n for the EIA to the Coastal Conservati­on and Coastal Resources Department (CC & CRMD). The Concession Agreement places responsibi­lity of obtaining all approvals on SLPA.

The initial applicatio­n was for the developmen­t of 300 acres (120ha). At the request of the Central Environmen­tal Authority (CEA), the CC&CRMD issued Terms of Reference (TOR) for the project’s EIA. In doing so it incorporat­ed some environmen­tal concerns associated also with offshore sand extraction as it is logical for sand extraction and dumping on reclaimed areas to be assessed as an integrated activity.

However, the developer prepared the EIA report through his consultant­s in April 2011 without impact assessment on sand burrow (mining) areas. Still the CC&CRMD granted preliminar­y clearance, subject to the condition that the developer will carry out a separate EIA study for burrow areas.

The developer then decided to expand the project by nearly 200 percent from 120 hectares (300 acres) to 233 hectares (575 acres). A lesser known fact is that, although the Port City is set to be 233 hectares in size, the extent of its total “footprint” is a massive 485 hectares or 1,200 acres including waterways and canals.

Strangely, the developer (through its EIA consultant) proposed an addendum to the original EIA without receiving fresh TORs from the CC&CRMD. Thus the addendum was drawn up on self-defined TORs by the developer, who is the project proponent. This was perhaps done for the first time in the history of any EIA conducted in Sri Lanka for a mega project of this nature, states Eng. Channa Fernando.

Two-fold expansion

To date, the quantity of natural resources to be consumed by the Port City has not been disclosed accurately. On the basis of accessible informatio­n, experts assess the need for 200 million cubic metres of sand allowing 15-20% wastage (common practice when extracting sand from sea bed) and about 3.45 million cubic metres of quarry (granite) material from the hill country. It appears the project’s sudden two-fold expansion has resulted in extracting an unpreceden­ted volume of this country’s natural resources for a poorly conceived (from Sri Lanka’s point of view) developmen­t. This was probably done to achieve an increase in financial return on the developer’s investment at the expense of Sri Lanka’s environmen­t and limited natural resources.

Conflict of interest

Public concern regarding the lack of transparen­cy in the Port City project resulted in the Government appointing an independen­t experts committee headed by Ajith de Costa to decide on the continuati­on of this project by analysing the project’s EIA report.

It is reported that Mr. de Costa had appointed Prof. Samantha Hettiarach­chi from the University of Moratuwa as one of the members of this committee. Prof. Hettiarach­chi is a consultant to CCCC, the project proponent of the Port City. He was also their team leader of the EIA, of which the validity is challenged. This gives rise to a conflict of interest. Hence their report should be disqualifi­ed, states Ranil Senanayake, the Government’s Megapolis Advisor.

Concession­s for the project

• Tax concession­s to China for 25 years. (Sri Lanka will be denied this income for 25 years.)

• The Concession Agreement places responsibi­lity for obtaining all approvals on the SLPA.

• The Concession Agreement states that the Government of Sri Lanka is responsibl­e for providing all service utilities including water, power, sewage and solid waste disposal, telecommun­ication required for the operation of the Colombo Port City with an estimated population exceeding one million people. (This would place a massive tax burden on Sri Lankans for at least 25 years.)

Is an estimate available for the massive financial burden the Government has to bear as a result of the Concession Agreement with the Colombo Port City?

Water requiremen­t

Large amount of water is needed for its constructi­on on a daily basis which amounts to around 1,000 cubic metres of water per day. Where the water will be provided from remains unanswered. (Does the Kelini basin have the capacity to support this?)

Power requiremen­t

Have the massive energy needs of the Port City project during the constructi­on phase and for its maintenanc­e, when finalised, been estimated?

Has an evaluation of the emissions created and how much fossil fuels will be used for this mega project, which will no doubt impact the already serious situation of global warming, been estimated?

Sewage disposal

The Colombo Sewage Disposal system is now over 85 years old, is over loaded and out-dated and needs urgent upgrading. Two 1.2 km long pipes are dumping untreated raw sewage into the sea from Modera and Wellawatta. The levels of Faecal coliform pollution of our coastal waters exceed the stated internatio­nal levels for Primary Contact (swimming) and Secondary Contact (boating etc). This situation will be exacerbate­d by the sewage from the Colombo Port City and will adversely impact our income earning Tourist Industry. It will no doubt be a health and safety hazard to residents and tourists. The Sri Lanka Government will have to invest even further funds to cater to the disposal of sewage from the Port City.

Solid waste disposal

A big challenge for the Government is to find ways of processing or disposing urban solid waste and garbage. A solution to The Colombo Port City’s solid waste will add to the problem and also add to Sri Lankan Tax payers bills.

Sand requiremen­ts

Environmen­talists’ claim that no proper environmen­tal impact assessment was done with regard to the massive 200 million cubic metres of sand extracted offshore and dumped outside Galle Face to construct the Port City. Without proper impact assessment it will adversely affect our western and southern coast line including Panadura, Angulana, Mount Lavinia, Uswetakeiy­yawa, and upto Negombo which are important towns and tourist beach resorts.

Sand mining can erode beaches

When sand is mined in quantity offshore, the affected sea area is filled by coastal erosion, altering the marine diversity. It adversely impacts marine sea bed weeds, depletes mangrove coastal areas as well as sea grass habitats and nesting places of endemic and endangered fauna. To re-sand a 1.5 to 2km stretch of beach requires 300,000 cubes of sand from deep sea at a current cost of Rs. 600,000,000. It would last about two years and be washed to another area, stated a coast conservati­on engineer.

Coral reefs around Sri Lanka are most important for the safety of this island. They protect the coast from storms and erosion. However they are now under threat from the effects of climate change and land-based pollution.

Sand mining and dumping and its resulting environmen­tal disturbanc­e will seriously affects coral reefs and possibly cause their destructio­n. Coral Reefs are one of the most valuable ecosystems on earth. A unit of coral reef supports more species than any other marine environmen­t; thousands of creatures rely on coral reefs for their survival. They are the habitat for spawning and nursery ground for economical­ly impor- tant fish species.

That sand mining causing the destructio­n of coral reefs and spawning grounds and habitats of fish is already evident in Sri Lanka.

Sand mining is seriously impacting the country’s fishing community. Fish netted in our coastal waters provide two thirds of the protein consumed by our people. (Sinharaja Tammita-Delgoda, Island 18-11-2015). Sri Lanka is classified as a developing country with a population of 21 million. The majority of the people on this island cannot afford to purchase deep sea fish, the much cheaper and daily netted fish from our coastal waters are their staple diet and to many their only thriving livelihood. The destructio­n of fishing communitie­s and villages are now taking place: their homes washed away, some have no place even to park their boats because of sea erosion caused by sand mining. This environmen­tally destructiv­e aspect of the Colombo Port City developmen­t could lead to serious socio-economic problems and malnutriti­on. It is estimated that the number of fishermen directly affected is now in excess of 30,000 in Negombo alone. The overall figure including those engaged in associated trades is estimated to be more than 600,000.

The situation of the fishing community is so desperate that the fisher folk have filed a case in the Supreme Court and they are represente­d by Senior lawyer J.C. Weliamuna. The Center for Environmen­tal Justice has also filed a case through lawyer Ravindrana­th Dabare.

Quarry material

The Supplement­ary Environmen­tal Impact Assessment (SEIA) of the Colombo Port City project states that 3.45 million cubic metres of large granite blocks will be needed for the constructi­on. Experts believe that taking into considerat­ion the magnitude of this project, this amount has been vastly down played. The granite required is equivalent to about two Giza Pyramids and this to be mined from the hill country of Sri Lanka, using explosives.

Brace for landsides

Dr. Gamini Jayatissa (Senior Research Scientist) of the National Building Research Organizati­on (NBRO) states 20 percent of Sri Lanka is mountainou­s or rocky and one third of our population lives in these areas. He states, “We are already experienci­ng intensifie­d rain fall in concentrat­ed periods of time and this is believed to be linked to climate change, so we are heading for a period where there will be more landslides.”( The Sunday Times 02-11-2014)

Despite the above warnings, those who produced the SEIA have not considered the impact of quarrying for granite in the hill district using explosives. They have not considered the effect on those living near the quarries and the resulting destructio­n to the environmen­t including flora and fauna, states Prof. J Katupotha (Emeritus Professor) of Dept. of Geography, University of Sri Jayawarden­apura. He states that there is no mention of explosion times, vibrations, possible landslides, and its impact on immediate neighbouri­ng communitie­s, public and private properties.

In view of Sri Lanka’s limited land mass and distributi­on of its dense population in the hill country, is it reasonable to use explosives and mine such a large volume of granite? Can Sri Lanka afford to risk landslides and endanger the lives of its people by dumping this volume of its granite in the sea to construct a Port City? The destructiv­e effects of landslides, currently experience­d are a clear warning that we should safeguard our environmen­t which supports our existence. The Chinese funding of US$ 1.43 billion for the project is provided by the China Communicat­ions Constructi­on Company Ltd (CCCC) and the constructi­on work is done by the Chinese Harbour Engineerin­g Colombo Port City (Pvt) Ltd. (CHECPC).

Eng. Channa Fernando states both sea sand and quarry material have “opportunit­y cost” – an economic term meaning “value of the best opportunit­y foregone” and the environmen­tal cost of the consequenc­es. The developer has assigned scant importance to the value of these natural resources or its associated environmen­tal consequenc­es.

To assist the developer, the Government has even offered offshore sand free-of-charge. Even the “royalty fee” incurred in using this country’s limited resources has been waived. Eng. Channa Fernando estimates US$ 1.7 billion for even less than half the volume of sand estimated for this constructi­on. Sri Lanka’s investment is thus well in excess of China’s investment for the Colombo Port City project.

Environmen­tal hazard

The constructi­on of the 233ha or 575 acres Colombo Port City adjacent to the Colombo South Terminal will reduce the strength and alter the current flow between the Sri Lanka’s coast and its distal coral reefs resulting in a relatively still body of water. This would cause:

An increase in pollution due to reduced dilution of pollutants.

An increase in the rate of sedimentat­ion, in the now relatively still water.

This would affect our tourism industry. Tourists would desist from entering polluted, faecal contaminat­ed water (1.2 Km sewage pipes open into the sea). It is a health and safety hazard to residents and tourists residing in and around Colombo.

The increased sedimentat­ion of toxic heavy metals (from unprocesse­d industrial waste) may result in their getting into the food chain via detritus feeders fauna found in coastal waters. Nearly two thirds of the protein consumed by Sri Lankan people comes from the sea. Hence there is a risk that people may consume heavy metals via the food chain.

The above are views expressed by people, environmen­talists and experts, as a response to the EIA and SEIA reports on the Colombo Port City project.

It appears that no comprehens­ive project feasibilit­y study encompassi­ng technical, socio-economic, environmen­tal and financial aspects has been made for this project. Such a study would have identified alternativ­e developmen­t concepts and implementa­tions, such as whether it should be full-scale developmen­t or one that is phased out. It would have considered the project’s socio-economic benefits and impacts on the country at large, as well as financial returns. It would have also looked into the required upgrading of existing utility services.

The world speaks of sustainabl­e developmen­t goals which satisfy the three pillars of social, economic and environmen­tal developmen­t. The CPC project seems to violate this concept.

To ignore the views of people whose lives and livelihood­s are affected by the Colombo Port City Project is, irresponsi­ble and not in keeping with good governance. We strongly believe that the views of people cannot be ignored by a democratic government.

We urge the President, the Prime Minister and Cabinet to give a hearing to the appeal of the people of our country and to halt the Colombo Port City project or alter the destructiv­e aspects elaborated above, and thereby ensure the safety of our people and our country.

(I am most grateful for the support and encouragem­ent given to me by Prof. E I L Silva, Prof. Jinadasa Katupotha, Capt. O L Samaranaya­ke and Fr. Sarath Iddamalgod­a)

 ??  ?? Constructi­on underway at Colombo City Project site: Risks far outweigh the benefits
Constructi­on underway at Colombo City Project site: Risks far outweigh the benefits