Sunday Times (Sri Lanka)

Offer by Railways sidetracke­d; China gets huge signal contract

-

continued from Page 1 new line for a fraction of the amount the Ministry now intends to spend. The Department recently installed signals at the Narahenpit­a railway station on the Kelani Valley line. Railway engineers replaced the old system with a modern user-friendly one and expect to do the same for all railway stations up to Kottawa by the end of the year.

The signals branch’s proposal was circulated among relevant officials. It was even briefly accepted by the ministry last year. But when a Technical Evaluation Committee ( TEC) report was sought to take it further, the initiative died a natural death.

Then, on April 12 this year, Transport Ministry Secretary Nihal Somaweera wrote to CNMIEC's Project Director, instructin­g him to start work on the installati­on of signalling, telecommun­ication and level crossing protection systems on the Matara- Beliatta section.

“SCAPC [ Standing Cabinet Appointed Procuremen­t Committee] decided to award the above contract to you and the Cabinet approval shall be obtained,” he wrote, in a letter seen by the Sunday Times. “You are kindly requested to commence the preliminar­y work with the pending approval of the Cabinet of Ministers regarding the above contract.”

Initiative­s of this nature -- at a cost as high as Rs 2.2 billion -cannot be implemente­d without Cabinet approval being granted first. Mr Somaweera told the Sunday Times there “may have been an omission” in the letter. He claimed that Cabinet sanctioned the project as far back as last year. He did not offer documentar­y evidence.

The project was given to CNMIEC because there was a provisiona­l sum of US$ 15mn within its existing contract for the extension of the railway line. “As the client, we can order work at any time under the provisiona­l sum,” Mr Somaweera said. “Since we have no money, the Ministry decided to use this for the signalling component. It is not a separate contract. We got a quotation from them. How can we go for a tender if we don’t have money?”

A provisiona­l sum is “an allowance usually estimated by the cost consultant and is inserted into tender documents for a specific element of the work that is not yet defined in enough detail for tenderers to price.” Mr Somaweera confirmed that a Cabinet memorandum has been submitted in this regard “for their informatio­n”.

“The track extension was given without signalling,” he continued. “How can we operate the railways without signalling? We have to pay back the loan but without operation we cannot get income. So we decided to give this out. In this way, we don’t have to ask for additional funds. We can use existing provisions.”

“It may be true that there is a provisiona­l sum,” said a senior official who did not wish to be quoted. “You can use this contingenc­y, but not for useful, wasteful projects. We are talking about just four stations.” Questions have also been raised about CNMIEC’s competence to carry out a signalling project. It has mostly implemente­d civil contracts. Mr Somaweera said the company would form a joint venture with a signalling firm.

Asked how it was decided that the project cost should be US$ 15mn, Mr Somaweera said the Ministry negotiated on the basis of estimates made by the relevant TEC. “It is the responsibi­lity of Technical Evaluation Committee to find out the exact cost and report the estimate to us,” he said. “Our decision, as administra­tors, was based on their recommenda­tion.” He said the head of the TEC -- J.I.D. Jayasundar­a, Chief Engineer Signa ls and Telecommun­ications of the Railways Department -- was answerable.

The Sunday Times found, however, that Mr Jayasundar­a did not head the TEC that evaluated the project. He was sidelined in favour of Palitha Samarasing­he, an Additional Secretary at the Ministry of Transport and former Chief Engineer Signals and Telecommun­ications. Mr Jayasundar­a was not even included as a member of the TEC.

Mr Somaweera also said it was not possible to compare the installati­on of signals at Narahenpit­a to the requiremen­ts of the Matara- Beliatta track because the former had only been an upgrade. “They made some improvemen­ts to the existing system at Narahenpit­a,” he maintained. “They did not set up a fully-equipped signalling system. So the scope is different.”

This claim was found to be untrue. The signals at Narahenpit­a were a new system designed by engineers and met all requiremen­ts. The Signals and Telecommun­ications Department also hopes to put in cables to replace tablets in future.

Newspapers in English

Newspapers from Sri Lanka